Distribution order lead timesThe following tables list the lead time components, the calendar, and availability type that are used to plan the distribution order lead times.
To plan a distribution order, you always use a supplying relationship. If a carrier is linked to the supplying relation, to perform the order offset, you can use transportation time. Otherwise, the supplying relationship supply time is used. Supply time For the planning of supply time, you can use the calendar of the supplying relationship’s supply source in the Supplying Relationships (cprpd7130m000) session. The calendar is retrieved as follows:
If no supply resource is defined, the item calendar is retrieved as follows:
| ||||||||||||||||