Purchase schedule cumulativesPurchase schedule cumulatives (CUMs) are used to do the following:
Cumulatives In Approvvigionamento, these CUMs are supported:
When a purchase schedule is released, LN inserts records in the previously mentioned sessions in this order:
In general, cumulatives are calculated and updated based on schedule number, CUM reset date, and transaction date, which can be the shipment date, receipt date, planned requirement date, or invoice date. The schedule number and the transaction date are determined when the transaction takes place. Nota You can reset the cumulatives in the Reimpostazione quantità cumulative (tdpur3230m000) and Reimpostazione quantità cumulative per Riga totale contratto (tdpur3230m100) sessions. Cumulative models In the Modello CUM field of the Parametri programma acquisti (tdpur0100m500) session, you can specify how the communicated cumulatives are used in company. These CUM models are available:
Nota For push schedules, goods are usually received against a blanket warehouse order and the purchase release usually contains clustered schedule lines. Received goods are distributed across the schedule lines with the oldest unfulfilled requirement of the type immediate or firm. Per ulteriori informazioni, consultare Clustering purchase schedule lines. Esempio Schedule Number 10000001
Istruzione 1. Select purchase schedule lines The purchase schedule lines are selected in the sequence of oldest unfulfilled requirement of the type Effettivo. Consequently, first receipts are booked on the requirement of 11 January, then on the requirement of 12 January , etc. Receipts can be booked on schedule lines for a maximum of the ordered quantity. In our example, a receipt of seven pieces is booked as follows:
Istruzione 2. Update purchase schedule lines The purchase schedule lines are updated in the Righe programma acquisti (tdpur3111m000) session.
Istruzione 3. Insert receipt details The receipt details are updated in the Programma acquisti - Ricevimenti (tdpur3115m200) session.
Istruzione 4. Update planned inventory transactions Planned inventory transactions are updated in Magazzino.
Istruzione 5. Update received cumulatives The received cumulatives are updated in the Quantità cumulative ricevute (tdpur3132m000) session.
Istruzione 6. Update required cumulatives The required cumulatives are updated in the Quantità cumulative richieste (tdpur3130m000) session.
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||