| Overview of purchase schedule handlingA purchase schedule is a timetable of planned supply of
materials. Purchase schedules support long-term purchasing with frequent
deliveries and are usually backed by a purchase contract. All requirements for
the same item, buy-from business partner, ship-from business partner, purchase
office, and warehouse are stored in one schedule. Purchase schedules are used
instead of standard purchase orders in cases where full visibility and time
phasing of material requirement information is required. Therefore, purchase
schedules provide a more detailed way to specify the delivery dates/times per
item. The following types of purchase schedules exist: Push schedule A list of time-phased requirements, generated by a central
planning system, such as Pianificazione aziendale or Progetti e commesse that is sent to the purchase business partner. Push schedules contain both a
forecast for the longer term and actual orders for the short term. A push
schedule is a nonreferenced schedule. Pull forecast schedule A list of time-phased planned requirements, generated by Pianificazione aziendale, that is
sent to the purchase business partner. Pull forecast schedules are only used
for forecasting purposes. To order the items, a pull call-off schedule must be
generated with the same schedule number as the pull forecast schedule. Similar
to a push schedule, a pull forecast schedule is also a nonreferenced schedule. Pull call-off schedule A list of time-phased specific requirements of purchased items,
triggered from Controllo assemblaggio, or Magazzino (KANBAN, Time-phased order point). A pull call-off schedule
is a referenced schedule.
Purchase schedule master data Before you can perform the purchase schedule
procedure: - Select the Programmi check box in the Parametri Approvvigionamento (tdpur0100m000) session.
- Specify the purchase schedule parameters in the Parametri programma acquisti (tdpur0100m500) session.
- Specify the purchase schedule master data.
Per ulteriori informazioni, consultare:
Before you can create a purchase schedule, you must
also: - Specify the following item data in the Articoli (tcibd0501m000) session:
- Set up a segment set as follows: Per ulteriori informazioni, consultare Utilizzo di set di segmenti.
- Specify patterns in the Schemi (tcccp0690m000) session.
- Specify the purchase schedule related parameters that apply to
an item and business partner combination in the Dati logistici righe contratti di acquisto (tdpur3102m000) or Articoli - Business Partner acquisti (tdipu0110m000) sessions.
- Store delivery patterns by warehouse, buy-from business
partner/ship-from business partner and item in the Schemi di consegna per Magazzino/BP/Articolo (tdipu0124m000) session. Based on the combinations
in this session, planned delivery moments can be generated in the Generazione momenti di consegna pianificati (tdipu0225m000) session.
- Generate planned delivery moments in the Generazione momenti di consegna pianificati (tdipu0225m000) session
to determine when an item can be delivered. The dates returned, which are
listed in the Mom. di consegna pianif. (Basati su spediz.) (tdipu0125m000) and Mom. di consegna pianif. (Basati su ricevimento) (tdipu0126m000) sessions, are used by Pianificazione aziendale for lead
time offsetting.
Nota If the Determinazione dei prezzi dei materiali in Approvvigionamento check box is selected
in the Parametri prezzi materiali (tcmpr0100m000) session, after setting up the material
pricing master data, LN can retrieve material price information for a schedule line. Push schedule procedure The following steps are or must be completed in the push
schedule procedure: - Generate a schedule header and lines
- Regenerate schedule lines
- Generate a purchase release (line)
- Approve the purchase release line
- Print the purchase release
- Insert authorizations
- Insert receipt details
- Insert cumulatives
- Reset the cumulatives and authorizations
- Update history and turnover data
Per ulteriori informazioni, consultare Programmi forniture. Pull forecast schedule procedure Based on the parameters and triggers, the following steps are
completed in the pull forecast schedule procedure: - Generate a schedule header and lines
- Regenerate schedule lines
- Generate a purchase release
- Approve the purchase release
- Print the purchase release
- Insert authorizations.
- Generate a pull call-off schedule
Per ulteriori informazioni, consultare Programmi richieste previste. Pull call-off schedule procedure Based on the parameters and triggers, the following steps are
completed automatically in the pull call-off schedule procedure: - Generate a schedule header
- Generate schedule lines
- Generate a purchase release
- Print the purchase release
- Insert receipt details
- Insert cumulatives
- Reset the cumulatives and authorizations
- Update history and turnover data