Release Plan (tsspc3240m000)

Use this session to release an existing group planning. You can release a complete group planning or select the groups and activities that must be released.

 

Selection Range
Activity Origin

The From and To fields define a range of: the Activity Origin.

Allowed values

Activity Origin

Level

The group planning level to be released.

Allowed values

Level

Group

The From and To fields define a range of: groups that must be released.

Activity Set Sequence

The From and To fields define a range of: activity sets in a group that must be released.

Planned Start Time

The From and To fields define a range of: the planned start time of the activities that must be released.

Planned Finish Time

The From and To fields define a range of: the planned finish time of the activities that must be released.

Options
Simulate

If this check box is selected, LN runs the release process in simulation mode. The results are not saved in the database. This process enables you to review the results before releasing the selected groups and activities.

Keep Existing Assignments for Service Orders

If this check box is selected, LN does not overwrite the existing assignments for service orders.

Note

This field is enabled only when the Activity Origin field is set to Service Order.

Keep Existing Assignments for Work Orders

If this check box is selected, Infor LN does not overwrite the existing assignments for work orders.

Note

This field is enabled only when the Use Assignments in Work Orders check box is selected in the Work Order Parameters (tswcs0100m000) session.

Keep Existing Assignments for Projects

If this check box is selected, LN does not overwrite the existing assignments for project.

Note

This field is enabled only when the Use Assignments check box is selected in the Project Planning Parameters (tppss0100s000) session.

Only Release if Group has an Allocated Resource

If this check box is selected, LN releases the group planning only if the group has allocated resources.

Delete Released Groups

If this check box is selected, LN deletes the selected groups after the release process.

Delete Released Activity Sets

If this check box is selected, LN deletes the selected activity sets after the release process.

Delete Released Activities

If this check box is selected, LN deletes the released activities after the release process.

Print Options
Process Report

If this check box is selected, LN generates process report. The report contains details of all activities that are released.

Error Report

If this check box is selected, LN generates error report. This report contains details of all warnings and errors that occurred during the release process.

 

Release

Releases an existing group planning or specific groups and activities that must be released.