Groups for Quality (tsspc3100m500)

Use this session to view and modify the group planning data for Non-Conformance Report and Corrective Action Plan.

 

Start Date Groups

The start date of the group. Infor LN displays the details of the groups with a start date later than the specified date.

Finish Date Groups

The finish date of the group. Infor LN displays the details of the groups with a finish date earlier than the specified date.

Allocated Engineer

The code of the allocated service engineer based on which the group data is filtered.

Group Set

The unique ID of the group set for which the attribute values are specified.

Group

The unique ID of the group.

Activity Origin

The origin of the activity.

Allowed values

Activity Origin

Check Resources for Attribute Values

If this check box is selected, Infor LN allocates resources for the Non-Conformance Report and Corrective Action Plan based on the attribute values.

Check Resources for Skills

If this check box is selected, Infor LN allocates resources for the Non-Conformance Report and Corrective Action Plan based on the skills.

Check Resources for Availability

If this check box is selected, Infor LN checks the availability of resources for the Non-Conformance Report and Corrective Action Plan.

Minimum Availability Percentage

The minimum availability percentage of the resource for the allocation.

Group Status

The least possible status of all the activities in the group.

Maximum NCR/CAP Status

The highest possible status of all the activities in the group.

Frozen

If this check box is selected, the group is frozen and you cannot add new groups to the existing groups.

Firm Planned

If this check box is selected, the group is firm planned and you cannot modify the start and finish date of the group.

Sort Method

The sorting method for the Non-Conformance Report and Corrective Action Plan activities in an activity set.

Allowed values

Sort Method

Keep Sequence of Activity Sets

If this check box is selected, Infor LN does not change the sequence of the activity sets when the specified group is planned.

Planned Start Time

The planned start date and time of the first activity set in the specified group.

Planned Finish Time

The planned finish date and time of the last activity set in the specified group.

Plan Method

The method to plan the Non-Conformance Report and Corrective Action Plan activities.

Allowed values

Plan Method

Total Activity Duration

The cumulative duration of activities for all the activity sets in the group.

Allocated Engineer

The engineer allocated to the specified group.

 

Initialize

Populates the data in the Start Date Groups field.

Initialize

Populates the data in the Finish Date Groups field.

Remove Allocated Resources

Deletes all the resources assigned to the selected order.

Show All

Displays all the groups defined for all the orders.