The start date of the group. LN displays the details of the groups with a start date later than the specified date.
Groups for Work Orders (tsspc3100m100)Use this session to view and modify group planning data for work orders.
Start Date Groups The start date of the group. LN displays the details of the groups with a start date later than the specified date. Finish Date Groups The finish date of the group. LN displays the details of the groups with a finish date earlier than the specified date. Allocated Resource The resources assigned to the specified group. Assigned resources are copied from group planning to the service order activity, work order activity or planned activity. Group The unique ID of the group. Frozen If this check box is selected, the group is frozen and you cannot add new groups to the existing groups. Firm Planned If this check box is selected, the group is firm planned and you cannot change the start and finish date of the group. Sort Method The sorting method for work order activities in an activity set. Allowed values Note
Keep Sequence of Activity Sets If this check box is selected, LN does not change the sequence of the activity sets when the specified group is planned. Check Resources for Attribute Values If this check box is selected, LN allocates resources for work orders based on attribute values. Check Resources for Availability If this check box is selected, LN checks availability of resources for work orders. Minimum Availability Percentage The minimum availability percentage of the resource for the allocation. Group Status The least possible status of all the activities in the group. Maximum Activity Status The highest possible status of work order that is assigned to the group. Planned Start Time The start date and time of the first activity set in the specified group. Planned Finish Time The finish date and time of the last activity set in the specified group. Plan Method The method to plan the work order activities. Allowed values Note
Respect Earliest Start Time If this check box is selected, LN considers the earliest start time to plan the work order activities. Note
Respect Latest Finish Time If this check box is selected, LN considers the latest finish time to plan the work order activities. The Planned Finish Time cannot be planned after the Latest Finish Time. Note LN re-plans the route for the activity. Respect Material Availability Date If this check box is selected, LN considers the Material Availability Date specified for the work orders in the Resource Planning Parameters (tsspc0101m000) session, to schedule the work order activities in a Group Set. Note
Total Activity Duration The cumulative duration of travel for all the activity sets in the group.
Initialize Populates the data in the Start Date Groups field. Initialize Populates the data in the Finish Date Groups field.
| |||