Group planning processTo generate the plan, LN does the following: Step 1. LN populates the activities in the group planning based on
the planning attributes
Note: If the activity set is frozen, LN does not allow you to add orders to an existing activity, but new orders can be manually added to an activity set. LN allows you to manually add new service orders to an existing plan, even though the activity set is frozen. Step 2. Sort the activities LN sorts the activities in groups and activity sets. By default, sorting is based on the latest finish time. Each activity set contains one order with the earliest of the latest finish time, that is also the earliest time the activity set can start and be used for sorting. Step 3. Plan forward against the calendar LN plans the sorted activities considering the time windows into account. Planning is based on the Plan Forward parameter in the Generate Plan (tsspc3200m000) session. Note: Planning can also be based on the route. You can use the Plan Method parameter in the Service Planning Parameters (tsspc0100m000) session. Step 4. Modify the plan manually LN allows you to modify the plan at two levels:
For example, for a day, when the work load within a group is satisfactory, the user can merge all activity sets in a group, resulting in a single group-activity set combination that contains many service orders. These service orders can be sequenced again before the plan is frozen. Note Merging of activity sets results in re-sorting and re-planning Step 5. Assign resources You can assign engineers to the activity:
You can define up to 20 skills for an activity. The required activity skills must meet the employee assigned for the activity between the planned start and finish time of the activity. Using the Group planning module, you can create a group of activities or buckets of work to be executed, that can be assigned to an employee/resource. LN allows you to assign the resources at these levels:
Note LN allows you to generate a default assignment. You can assign an engineer to a service order activity directly, based on the service type. However, the assignment generated by group planning is considered before the default assignment. Step 6. Recalculate planned start and finish time LN calculates the new start and finish times. When the new planned start and finish times are known, including travel durations, the slack or shortage of time can be displayed to the user (planner) for every group assigned to a resource. Step 7. Release group planning The group planning activity data is copied to the corresponding service order activities, work order activities and planned activities using update activities from the Group Planning session. For service orders, the updated travel date/time fields are also copied. Use the Release Plan (tsspc3240m000) session to release the group plan. Note LN allows you to delete the groups from group planning when the resources and the planned start and finish time, are updated.
| |||