Estimate at Completion

This bar chart displays the BAC, EAC and VAC for all the projects assigned to a project manager. Variance at Completion (VAC) value = Budget at Completion (BAC) - Estimate at Completion (EAC). A negative variance at completion indicates a cost overrun. A positive variance at completion indicates a cost under-run. You can use the toggle option, to view the Variance at completion bar for all the projects. If the VAC is negative, the result is displayed in Red.

[...]