| How to use cost forecastLN uses one of the following methods for a project cost
forecast. The method is determined by the Leading Forecast Method list in the Project Accounting Parameters (tpppc0500m000) session: - Estimate-at-completion (EAC): The expected total cost at the end of the project.
- Estimate-to-complete (ETC):
The expected cost for the remaining work.
- Estimated-extra-costs
(EEC): The total expected cost for all remaining work that is not yet budgeted.
The decision of the Leading Forecast Method results in different
representations of the forecast in:
- Control Inquiries (tpppc4850m000).
- Performance Measurement (tpppc5840m000).
- Performance Measurement using EVM (tppss0702m000).
- Display Financial Analysis (tppss0701m000).
- Generate Financial Interim Results (tpppc2260m000).
If the leading forecast method is the estimate at
completion (EAC): - The estimated extra cost
(EEC) is not displayed during entry of the Estimate at completion (EAC).
- The variance at
completion (VAC) in the Control Inquiries (tpppc4850m000) session, the Performance Measurement (tpppc5840m000) session, and the Performance Measurement using EVM (tppss0702m000) session is: Budget at completion (BAC) - Estimate at
completion (EAC).
- The forecast cost in the Control Inquiries (tpppc4850m000) session shows the entered forecast amount and forecast
quantity.
- The estimate at
completion (EAC) in the Performance Measurement (tpppc5840m000) session and the Performance Measurement using EVM (tppss0702m000) session shows the entered forecast amount.
- The entered forecast
amount can be displayed as planned cost in the Display Financial Analysis (tppss0701m000) session. The entered Estimate at
completion (EAC) is transferred to an Estimate to complete (ATC) figure. The
following calculation is used: Estimate to complete (ETC) = Estimate at
completion (EAC) - Actuals.
- In the tpppc2260m000
session, the forecast amount is taken into account. The entered Estimate at
completion (EAC) is transferred to an Estimate to complete (ETC). The following
calculation is used: Estimate to complete (ETC) = Estimate at completion (EAC)
- Actuals.
If the leading forecast method is Estimate to
complete (ETC): - The Estimated extra cost
(EEC) is not displayed during entry of the Estimate to complete (ETC).
- The Variance at
completion (VAC) in the Control Inquiries (tpppc4850m000) session, the Performance Measurement (tpppc5840m000) session, and the Performance Measurement using EVM (tppss0702m000) session is:
- Budget at completion
(BAC) - Estimate to complete (ETC)- Actual costs.
- The Control Inquiries (tpppc4850m000) session shows the entered forecast amount and forecast
quantity.
- The Estimate at
completion (EAC) in the Performance Measurement (tpppc5840m000) session and the Performance Measurement using EVM (tppss0702m000) session is calculated from the entered forecast
amount. The formula used in this calculation is Estimate at completion (EAC) =
Actuals + Estimate to complete (ETC).
- In the Display Financial Analysis (tppss0701m000) session, the entered Estimate to
complete (ETC) forecast amount can be displayed as planned cost.
- In the Generate Financial Interim Results (tpppc2260m000) session, the Estimate to complete
(ETC) forecast amount can be taken into account.
If the leading forecast method is Estimated extra
cost (EEC): - During entry of the
forecast, the values of the other forecast methods are not calculated and shown
as zero.
- The Variance at
completion (VAC) in the Control Inquiries (tpppc4850m000), the Performance Measurement (tpppc5840m000), and the Performance Measurement using EVM (tppss0702m000) is Cost variance (CV) - Estimated extra cost (EEC).
Where Cost variance (CV) is performed (BCWP) - Actuals.
- The forecast cost in the Control Inquiries (tpppc4850m000) session shows the entered forecast amount and forecast
quantity.
- The Estimate at
completion (EAC) in the Performance Measurement (tpppc5840m000) session and the Performance Measurement using EVM (tppss0702m000) session cannot be calculated and is set to zero.
- In the Display Financial Analysis (tppss0701m000) session, the entered Estimated extra
cost (EEC) forecast amount can be displayed as additional planned cost on top
of the budget.
- In the Generate Financial Interim Results (tpppc2260m000) session, the Estimated extra cost
(EEC) forecast amount can be taken into account.
| |