| Cost plus invoicingYou can maintain and
control the invoicing of cost plus projects and extensions in Project. Invoicing amounts
are based on the actual costs plus a markup, or the sales price/rate for the
product, or the service extended to the customer. LN displays the billing amounts and
quantities, based on the effort spent, on the contract lines of type Cost Reimbursement and Time & Materials. You can create a business partner's invoice only when
you incur the actual costs. To use cost plus invoicing: -
In the Contracts (tpctm1100m000) and Contract Lines (tpctm1110m000) sessions, ensure to do the following: - Set Contract Type to either Cost Reimbursement or Time & Materials,
- Set Invoice Type to Cost-Plus.
- Specify a project that is linked to the relevant contract
line.
- Register costs on the project. LN then registers the
costs on the contract line.
- Assign the revenue codes
in the Assign to Revenue Codes (tppin0810m000) session.
- Record the actual costs
in the Cost Entry Overview (tpppc2811m000) session. The options are:
- By element/ activity
- By cost type
- By control code
- By cost object: If you define
an element with the Elements (tpptc1100m000) session or an activity with
the Activities (tppss2100m000) session, use the Cost Control check box to indicate whether you want
to record project costs for the element or activity. If this check box is cleared, Project aggregates the element costs
to the parent element.
- Confirm the costs in the Approve Costs (tpppc4811m000) session.
Process the transactions in the Process Transactions (tpppc4802m000) session. Using this session you post the
confirmed costs to the project history and Financials. Note:
This is relevant only for costs registered for a project. LN approves and processes
the costs that are not part of the project. - Set the transactions to To be Invoiced using the Cost-Plus Transactions to be Invoiced (tppin4810m000) session.
- Process the transactions
to Invoicing using
the Transfer Transactions to Invoicing (tppin4200m000) session.
In Invoicing: - Confirm future invoices.
- Check invoice headers.
- Compose, print, and post
invoices to Accounts Receivable.
The associated revenues
are defaulted to Project Progress for transaction processing. | |