The order group for which you want to display or modify data.
Production Order Group - Production Orders (tisfc0501m100)Use this session to display the contents of an production order group. In addition, you can use the options in the appropriate menu to release production orders, report production as completed, backflush material and hours, and close production orders. You can also add or remove production orders to an order group. Source of orders in this session You can create order groups by carrying out the following two steps:
Or you can transfer orders from the Enterprise Planning package using the following session:
Production Order Group The order group for which you want to display or modify data. Total Grouped Orders The number of production orders in the JSC order group. Group Description The description of the order group for which you want to display or modify data. Grouped Order Quantity The total order quantity of all the orders in the order group. Note If the individual order quantities are in different units of measurement, this field is meaningless. Production Order An order to produce a specified quantity of an item on a specified delivery date. Item The end item of the production order. Quantity Ordered The order quantity to be produced. Production Start Date and Time The date that the production is planned to start. Delivery Date This date is created by Configurator or the Job Shop Control module when the order is created. It is initially the date when the buyer has requested delivery, but LN will alter this date if the planning is changed. This date is affected by the following parameters:
Warehouse The warehouse where the end-items or subassemblies will be stored after delivery. Order Status The status of the production order. Task The task used as the selection criterion in the Create Production Order Group (tisfc3250m000) session. Work Center The work center used as the selection criterion in the Create Production Order Group (tisfc3250m000) session. RoutingGroup The routing group used as the selection criterion in the Create Production Order Group (tisfc3250m000) session. Machine The machine used as the selection criterion in the Create Production Order Group (tisfc3250m000) session. Operation The operation used as the selection criterion in the Create Production Order Group (tisfc3250m000) session. Operation Status The status of the operation used as the selection criterion in the Create Production Order Group (tisfc3250m000) session. Physical Location The name or description of the location where the orders are processed. You can also use this field for any other information about the orders that is common to the group. You can update this field for all members of the group together with the Update Physical Location for Production Order Groups (tisfc0210m000) session. Note The physical location referred to in this field is not in any way related to a warehouse location. Item Group The item group used as a selection criterion for this order in the Create Production Order Group (tisfc3250m000) session. MaterialPlanner The material planner used as a selection criterion for this order in the Create Production Order Group (tisfc3250m000) session. Shop FloorPlanner The shop floor planner used as a selection criterion for this order in the Create Production Order Group (tisfc3250m000) session. Product Line The product line used as a selection criterion for this order in the Create Production Order Group (tisfc3250m000) session. ProductClass The product class used as a selection criterion for this order in the Create Production Order Group (tisfc3250m000) session. SelectionCode The selection code used as a selection criterion for this order in the Create Production Order Group (tisfc3250m000) session. Initially hidden fields Moment of Completion Posting The moment when LN posts the financial transactions for the completed quantities to Financials. For more information, see Moment of Completion Posting.
Remove Order from Production Order Group Click to remove the order that is currently selected from the group. Note You cannot Undo this action. To regroup the order, you must select Add Order to Production Order Group from the appropriate menu. No Help topic is associated with this item. No Help topic is associated with this item.
| |||