| Using up remaining stock of outdated itemsOften, new items are introduced that, make other items obsolete. The
obsolete items are no longer deliverable or the items are no longer
manufactured. If an outdated item is used as material in a bill of material (BOM), you must replace
the material by a replacement item with the same specifications. If a quantity
of outdated material remains in stock, it must be used up first. Restrictions - Use-up materials and alternative materials have the same net quantity as the standard material.
- Use-up materials and alternative materials have exactly the
same values of characteristics such as the scrap and yield as the standard
material.
- Use-up materials and alternative materials have the same
material-routing relationships as the standard item.
- If a component on a BOM line is a standard item, that is, an item with an
empty project segment, the associated use-up and alternative materials
must also be standard components.
-
If a component on a BOM line is a project item, that is, an item with a filled project
segment, the associated use-up and alternative materials' project segments must
be either: - Filled with the same project as the main item's project
segment
- Empty (the alternative is a standard item)
- If a component on a BOM line is a phantom, you cannot define a use-up material or
alternative material for that component.
Checks for use-up materials At any of the following moments, depending on parameter
settings, LN can check
whether you must use any use-up material: - When you generate planned production orders in the Enterprise Planning package.
- When the system generates a production order in the Job Shop Control module,
or if you release a production order.
- When you run the Generate Alternatives for Estimated Materials (ticst0216m000) session for
existing production orders.
- When you generate an outbound advice in the Warehousing package.
For more information, refer to Searching for alternative and use-up materials.. To use revisions and lot control instead of use-up materials If you use the Engineering Data Management (EDM) module to control changes in a bill of material (BOM) and you link
subsequent revisions to the same item code on a BOM line, you cannot apply the use-up functionality. For that situation, you can apply lot control and use the FIFO outbound
method. That outbound method ensures that you use up the outdated revision
before you take the new revision. | |