Example 1: Activity has not yet started

Activity A has not yet started. No hours have been spent, there is no project structure, and there is no detailed capacity planning.

  • Activity duration (project days): 15
  • Rough capacity requirement : 200
  • Earliest start date : day 4 week 44 year 92
  • Percentage completed : 0%

The current date lies before the earliest start date. The following figure depicts activity A being carried out:

[...]
WWorkdays
_Non-workdays

The capacity load table assigned to the activity is shown in the following figure:

[...]

The capacity for activity A is 200 hours. The capacity load per week is as follows:

WeekNumber of daysPercentage of Activity DurationPercentage of Capacity RequirementDifference Compared to Prev. Wk.Capacity Requirement (per Week)
44-92213%17.3%17.3%34.6
45-92640%40.0%22.7%45.4
46-92960%40.0%0.0%0.0
47-921280%70.0%30.0%60.0
48-921280%70.0%0.0%0.0
49-9215100%100.0%30.0%60.0