Reporting production orders as completedReporting orders completed When production is ready, you must report the production order completed. You can do this in the following sessions: After you have reported a production order completed, you can still process material issues for the production order, or post hours to it. Quality management In certain situations you cannot report a production order completed before the inspection order for the operation has been processed. Blocked operations You cannot report a production order completed, if one of its operations is blocked. Completion of operations If the Reporting Method for Previous Operations field in the Production Order Parameters (tisfc0100s000) session is None, all operations must be reported completed before you can report the production order completed. If the Reporting Method for Previous Operations field in the Production Order Parameters (tisfc0100s000) session is Automatic or Interactive you can report a production order and its operations completed at the same time. Posting of end products If you use the Report Orders Completed Globally (tisfc0206m000) session, LN posts the current planned quantity of the product to inventory. The Tools Requirement Planning (TRP) module When you report a production order completed, the tool's life of the used tools is reduced. JSC order groups If you are using order groups, you can report completed all the production orders in a group simultaneously. Use the Report Orders Completed Globally (tisfc0206m000) session and select the Production Order Group check box.
| |||