Work Center 360 (timfc1501m000)

Use this session to check work center capacity and utilization in order to carry out production orders on schedule. If problems occur, they can be early distinguished to take suitable measures.

 

Week Capacity [Hours]

The weekly capacity of each resource unit in the work center. This value is used to calculate the normal capacity of a work center for each week, which is displayed in work center utilization reports.

Queue Time

The amount of time that an order remains at a work center before setup, or work is performed.

The queue time is used in lead time calculation. The queue time is expressed in days or hours. The days or hours must be interpreted as days and hours in the working time calendar that is linked to the work center.

Basic Day Capacity

The daily capacity of each resource unit in the work center. This value is used to calculate the normal capacity of a work center for each day, which is displayed in work center utilization reports.

Wait Time

The time that an order remains at a work center after an operation is completed until it is moved to the next operation.

LN does not plan wait times according to a specific calendar. Planning of the wait time is based on a 7 * 24 hours week schedule.

A typical example is the time required for drying after the application of paint.

When LN calculates the start times and end times of planned orders based on the routing, LN takes the wait time into account.

The plan buffer enables you to build in a certain tolerance between successive operations, which makes it possible to shift operations.

The wait time is expressed in days or hours. The days or hours do not relate to a calendar. The availability of time is considered as 24 hours a day, seven days a week.

Note

This field is not used if the Work Center Type field is Costing Work Center.

Number of Machines

The number of machines that is available for production on the work center. This value can be calculated and updated in the Calculate Resources (tirou0201m000) session.

LN searches for all machines allocated to a work center using of the Machines (tirou0102m000) session. The calculation for the number of machines for a work center:

Number of machines = Sum of weekly capacities of all
			 machines linked to the work center / Weekly capacity of the work
			 center

The work center's weekly capacity is defined in the Week Capacity [Hours] field.

The number of machines and the number of operators that is linked to a work center is used to calculate the work center's available capacity.

Example

Work center A40 hrs/week
Machine A40 hrs/week
Machine B60 hrs/week

 

Number of machines = (40+60)/40 = 2.50
Move Time

The time that a semifinished good is in transit from one operation to the next operation. After the last operation, the move time is the time required to transfer the finished good to the warehouse.

Move time is one of the lead-time elements LN plans according to a specific calendar.

Number of Operators

The number of operators that is available to the work center. This value can be calculated and updated in the Calculate Resources (tirou0201m000) session.

Each work center is a department. LN searches for all operators assigned to the department using the Employees - General (tccom0101m000) session, and calculates the weekly capacities. The calculation for the number of operators for a work center:

Number of operators = Sum of weekly capacities of all
			 operators linked to the work center / Weekly capacity of the work
			 center

The employees' weekly capacities are entered in the Employment field in the Employees - People (bpmdm0101m000) details session. The work center's weekly capacity is defined in the Work Centers (tirou0101m000) session.

The number of machines and the number of operators that is linked to a work center are used to calculate the work center's available capacity.

Example

Today's date: 2000-11-07
Work center A: 40 hrs/week
EmployeeFirst dateLast dateHrs/week
A2000-01-012000-01-0140
B2000-01-012000-06-0120
C2000-01-01030

 

Number of operators = (40 + 30) /40 = 1.75
Desired Queue

The difference between the output and input of a work cell required by the user. This value is the default for initial queue calculations.

Print Instructions

If you use a microrouting, you can define instructions for production orders for each operation and for each operation step. If the value of this field is Yes, those instructions are printed.

Related topics

Work Center

A specific production area consisting of one or more people and/or machines with identical capabilities, that can be considered as one unit for purposes of the capacity requirement planning and detailed scheduling.

Work Center Type

The work center type.

Allowed values

Work Center Type

Related topics

ParentWork Center

A work center that is subdivided into subordinate work centers.

Shared Work Center Type

Specification of the work center.

Related topics

Critical in Planning

If this check box is selected, the work center is critical. As a result, the work center is included in the bill of critical capacities used in Enterprise Planning.

Company

A working environment in which you can carry out logistic or financial transactions. All the transaction data is stored in the company's database.

Depending on the type of data that the company controls, the company is:

  • A logistic company.
  • A financial company.
  • A logistic and a financial company.

In a multisite structure, some of the database tables can be unique for the company and the company can share other database tables with other companies.

Subcontractor

The subcontractor, if the Work Center Type field is Subcontracting Work Center.

Note

You cannot specify this field if the SubcontractorIndependent check box is selected in the Work Centers (tirou0101m000) session.

Enterprise Unit

A financially independent part of your organization that consists of entities such as departments, work centers, warehouses, and projects. The enterprise unit's entities must all belong to the same logistic company, but a logistic company can contain multiple enterprise units. An enterprise unit is linked to a single financial company.

When you carry out logistic transactions between enterprise units, these are posted in the financial companies to which each enterprise unit is linked. You can define intercompany trade relationships between enterprise units to determine the terms for internal trade between these units. To use invoicing and pricing between enterprise units, you must link the enterprise units to internal business partners.

You can use enterprise units to do separate financial accounting for parts of your business. For example, you can define enterprise units for separate parts of your organization that belong to one logistic company, but that are located in different countries. The accounting of each enterprise unit is performed in each country's national currency, and in the financial company linked to the enterprise unit.

Operation Rate Code

The code linked to the work center and used as the work center rate.

Note

You must define operation codes in the Operation Rate Codes (ticpr0150m000) session.

This field is only enabled if:

  • The Type of Operation Rates parameter in the Standard Cost Calculation Parameters (ticpr0100m000) session is Work Center Rate or Task Relationship/Work Center Rate.
  • The Work Center Type is not Subcontracting Work Center.
Shop Floor Warehouse

A warehouse that stores intermediate inventory in order to supply work centers. A shop floor warehouse is linked to an individual work cell, an assembly line, or one or more work centers. A shop floor warehouse can be supplied with goods using replenishment orders, or by pull-based material supply.

The pull-based material supply methods are:

  • Order Controlled/Batch (only applicable in Assembly Control).
  • Order Controlled/SILS (only applicable in Assembly Control).
  • Order Controlled/Single (only applicable in Job Shop Control).
  • KANBAN.
  • Time-Phased Order Point.

The items stored in the shop-floor warehouse are not part of the work in process (WIP). When items leave the shop floor warehouse for use in production, their value is added to the WIP.

You can only enter a value if the Use of Shop Floor Warehouses check box in the Production Order Parameters (tisfc0100s000) session is selected.

The value of the Warehouse Type field in the Warehouses (tcmcs0103s000) session must be set to Shop Floor.

Backflush Employee

The employee number to which hours are posted in People using backflushing.

Queue Time

The amount of time that an order remains at a work center before setup, or work is performed.

The queue time is used in lead time calculation. The queue time is expressed in days or hours. The days or hours must be interpreted as days and hours in the working time calendar that is linked to the work center.

If the Time Unit field is Days, LN rounds the entered values of the lead times to integer values.

Costing Work Center

A work center, linked to a planning work center, that is used to calculate the end item unit costs, WIP transfers, and production results used to hold the financial transactions related to production orders.

The link between a costing work center, and a planning work center enables you to replan production order operations again. If required, you can change the work center that is used to carry out an operation without modifying the costing process.

Note

If the work center is of the Sub Work Center type, the costing work center of the sub-work-center's main work center is automatically displayed. However, you can change the costing work center in this field.

Related topics

Constraint Type

Specify the type of constrained type for the work center.

Allowed values

  • Time Fence
  • Plan Horizon
Constraint Time Fence

A reference date against which processes or statuses are evaluated.

Example

The assembly order time fence on an assembly line defines the end date of the period for which assembly orders must be created. If this time fence is 100 days, assembly orders must be created for product variants whose planned offline date is between now and 100 days. Similarly, a time fence can define when line station orders must be frozen, updated, and so on.

Use rough PCS capacity requirement

In PCS network planning, the work center's capacity can be consumed by:

  • PCS rough capacity, which is defined in the Activities (tipcs4101m000) session
  • Capacity required for JSC production orders and planned production orders in Enterprise Planning.

This check box determines how the work center's capacity is consumed:

  • If this check box is cleared, the work center's available capacity is consumed by the capacity required for the JSC production orders and planned production orders in Enterprise Planning. The rough capacity requirements defined in the Activities (tipcs4101m000) session are not taken into account.
  • If this check box is selected, the PCS rough capacity defined for activities in PCS, and the capacity required for JSC production orders and planned production orders in Enterprise Planning are subtracted from the work center's available capacity. Therefore, double consumption of work center capacity occurs.
Device for Printing Labels

The printer where you print the labels for completed production orders.