Items - Costing (ticpr0107m000)

Use this session to list or maintain cost-related data for items.

Note

For a purchased item, the standard costs in this session are calculated based on the Price Priority levels in the Cost Calculation Codes (ticpr1100m000) session.

Performance aspects

The settings in this session could affect system performance and database growth. For more information, refer to Cost component setup.

 

Item

The item to which the costing data is applied.

Surcharges by Item

If this check box is selected, surcharges can be defined by item.

Related topics

Surcharges by Warehouse

If this check box is selected, surcharges can be defined by warehouse.

Related topics

Combined Ownership Allowed

If this check box is selected, the standard cost for items with the customer furnished material check box selected will have the standard cost holding the company part and the possibility to calculate the customer owned value.

Aggregated Material Cost Component

The aggregated cost component to which the item's total material costs are linked.

Aggregated Operation Cost Component

The aggregated cost component to which the total operation costs for the item are linked.

Aggregated Surcharge Cost Component

The aggregated cost component to which the total surcharges are linked.

Currency

The currency that is used to express the standard cost. The usage of this field depends on the currency system that is set in the Companies (tcemm1170m000) session.

  • Dependent or Standard
    If your company's currency system is Dependent or Standard, you can enter any currency in this field to express the standard cost.
  • Independent
    If your company's currency system is Independent, you cannot change this field. However, you can select the local currency or one of the reporting currencies by clicking Rotate Currency.
  • Single
    If your company's currency system is Single, you cannot change this field. The standard cost currency is the local currency, which is displayed in this field.
Include Landed Costs

If this check box is selected, landed costs are included in the calculations.

Landed Costs Set

Select the landed costs set to be added to the item.

Standard Cost

The item's standard cost that consists of material costs, operation costs, and standard cost surcharges.

Material Costs

The estimated material costs that consist of the total material costs and the total standard cost surcharges that are required to purchase or produce the item.

Operation Costs

The estimated operation costs that consist of the total operation costs and the total standard cost surcharges to purchase or produce the item.

Last Calculation Date

The last date the estimated standard cost of the item has been changed.

Standard Cost Component Scheme

The code to which detailed cost components are linked. You must enter a scheme if you want to report detailed cost components for an item in the effective cost-component structure.

You must define the scheme in the Cost Component Scheme (ticpr0109m000) session. You must link detailed cost components to the scheme in the Standard Cost Scheme Details (ticpr0110m000) session.

Actual Cost

The total actual costs for the customized item.

These costs include the:

  • Material costs
  • Operation costs
  • Standard cost surcharges
Note

The actual cost is only calculated for customized items.

Material Costs

The real material costs for the customized item. These costs are, for example, purchase costs and warehouse costs (inventory transfers). The total material costs can also include standard cost surcharges.

Operation Costs

The real operation costs for making the customized item, for example, direct and indirect production hours, costs of subcontracting operations, and actual cost surcharges.

Last Calculation Date

The last date the actual cost of the item has been changed.

 

Actualize Cost Comp Structure for Configurable Item

Actualizes the effective cost component structure of generic items with order system FAS.