| Request for Quotation Lines (tdpur1502m100) Response Date Due The number of days after which the response line is due. Note - If a negative value is displayed, the response line is
already due and the number of days after the response date is displayed.
- If the response line status is set to Accepted or Processed, no value is specified in this field.
Alternative The request for quotation (RFQ) line's sequence number, which is
greater than one if it includes an item that can be an alternative for the
preferred item. You must manually specify alternatives in
the Request for Quotation Lines (tdpur1502m000) session. Example The sequence numbers defined in the current
field, represent the RFQ lines in the most suitable alternative sequence. So,
sequence number one represents the first preferable item that can be an
alternative for the originally preferred item, sequence number two represents
the second item that can be an alternative, and so on. Item The raw materials, subassemblies, finished products, and tools
that can be purchased, stored, manufactured, and sold. An item can also represent a set of items handled as one kit,
or which exist in multiple product variants. You can also define nonphysical items, which are not
retained in inventory but can be used to post costs or to invoice services to
customers. The examples of nonphysical items: - Cost items (for example, electricity)
- Service items
- Subcontracting services
- List items (menus/options)
The item code can be blank, which means bids are requested
for a new item. You can add a text to describe the item. When a response line that is linked to the RFQ line receives the Accepted status, the item code becomes mandatory. Note If the warehouse is WMS controlled: - And the Inbound BOM/List Items check box is cleared for the
warehouse in the WMS Interface Parameters (whwmd2105m000) session, you
cannot enter a list item of the type kit in this
field.
- And the Serials in Inventory check box is cleared for the
warehouse in the WMS Interface Parameters (whwmd2105m000) session, you
cannot enter a serialized item for which the Serials in Inventory check box is selected in the Item - Warehousing (whwmd4100s000) session.
- And the Serials Not in Inventory check box is cleared for the
warehouse in the WMS Interface Parameters (whwmd2105m000) session, you
cannot enter a serialized item for which the Serials in Inventory check box is cleared in the Item - Warehousing (whwmd4100s000) session.
- And the Lots Not in Inventory check box is cleared for the
warehouse in the WMS Interface Parameters (whwmd2105m000) session, you
cannot enter a lot controlled item for which the Lots in Inventory check box is cleared in the Item - Warehousing (whwmd4100s000) session.
Effectivity Unit A reference number, for example a sales order line or a project
deliverable line, that is used to model deviations for a unit effective item. Note If the warehouse is WMS controlled, and the Effectivity Units check box is cleared for the
warehouse in the WMS Interface Parameters (whwmd2105m000) session, you
cannot enter an effectivity unit in this field. RFQ Quantity The quantity that must be delivered according to the terms on
the order line. The quantity is expressed in the purchase unit or the sales
unit of the item. Unit The purchase unit in
which the items on the request for quotation (RFQ) line are expressed. Receipt Date The date on which the items, for which you send the request for
quotation, are scheduled to be delivered. Note - The receipt date is copied to the purchase order, or
purchase contract, when you copy the RFQ in the Convert RFQs (tdpur1202m000) session. This happens
after you accept the RFQ response from the bidder.
- The receipt date cannot be before the request for quotation date.
- The receipt date cannot be later than the response date.
Status The status of the RFQ line. RFQ Origin The request for quotation (RFQ) line's origin. Example When you create the RFQ line in the Request for Quotation Lines (tdpur1502m000) session, the Origin is Manual. Standard Description If this check box is selected, LN prints both the
standard item description and the specific request for quotation (RFQ) line
text. If this check box is cleared, LN prints only the
specific request for quotation (RFQ) line text. Item Cross Reference The alternative way of communicating with the bidder about
items. Item Code System The item code system's code. The
item code system is used to search for an item in an alternative way, for
instance by the bidder's item code. Note You can specify this field only if the Item Cross Reference field is ICS. Cross Reference Item The item code that is used to indicate the item in the Item field. The Item Cross Reference field determines the item code
that you can select. Note The MPN must have the status Approved or For Approval on the RFQ Date. Preferred Manufacturer Part Number Target Price The target price that is desired for the item on this RFQ
line. Default value The Purchase Price from the Items - Purchase (tdipu0101m000) session. Note If you use landed costs, this price should include these costs. Currency A generally accepted medium of exchange such as coins, treasury
notes, and banknotes. The following currency types are available in LN: - Home currency, which is used internally by companies to
calculate costs, record budgets, and register tax amounts
- Transaction currency, which is used in transactions with
business partners, such as orders and invoices
Price Unit The item unit in which an item's purchase price is expressed.
This unit can differ from the item's inventory unit. Average Purchase Price The average purchase price which is based on cumulative
purchases or on the current inventory, as specified in the Method of Calculating Average Purchase Price field of
the Purchase Order Parameters (tdpur0100m400) session. Latest Purchase Price The purchase price that is displayed on the most recent invoice
received for the item on this RFQ line. Average Landed Cost A cost component's average landed cost, which is based on
cumulative purchases or on the current inventory, as specified in the Method of Calculating Average Landed Cost field of the Landed Costs Parameters (tclct0100m000) session. Default value The Average Landed Cost from the Item Actual Landed Costs by Cost Component (tclct3501m000) session. Latest Landed Cost A cost component's latest landed cost. Default value The Latest Landed Cost from the Item Actual Landed Costs by Cost Component (tclct3501m000) session. Warehouse The warehouse where the
items must be delivered. Default value LN retrieves the default warehouse from: - The Requests for Quotation Overview (tdpur1501m000) session.
- If no delivery warehouse (address) is defined in the Requests for Quotation Overview (tdpur1501m000) session, LN retrieves the delivery
address from the Purchase User Profiles (tdpur0143m000) session.
- If no delivery warehouse (address) is defined in the Purchase User Profiles (tdpur0143m000) session, LN retrieves the delivery address from the Items - Purchase (tdipu0101m000) session.
- If no delivery warehouse (address) is defined in the Items - Purchase (tdipu0101m000) session, LN retrieves the delivery address from the Items (tcibd0501m000) session.
Receipt Address The address of the warehouse or place where the goods must be
delivered. Default value LN retrieves the default warehouse address from: - The Requests for Quotation Overview (tdpur1501m000) session.
- If no delivery warehouse (address) is defined in the Requests for Quotation Overview (tdpur1501m000) session, LN retrieves the delivery
address from the Purchase User Profiles (tdpur0143m000) session.
- If no delivery warehouse (address) is defined in the Purchase User Profiles (tdpur0143m000) session, LN retrieves the delivery address from the Items - Purchase (tdipu0101m000) session.
- If no delivery warehouse (address) is defined in the Items - Purchase (tdipu0101m000) session, LN retrieves the delivery address from the Items (tcibd0501m000) session.
Note If you have defined a warehouse in the Warehouse field,
you must fill this Receipt Address field. Start Receipt Period The start date of the period that the items, for which you send
the request for quotation, are scheduled to be delivered. Default value LN retrieves the default start date from the Requests for Quotation Overview (tdpur1501m000) session. Note The start date is copied to the purchase order, or purchase
contract, when you copy the RFQ line in the Convert RFQs (tdpur1202m000) session. This happens
after you accept the RFQ response from the bidder. You cannot define a receipt period if a receipt date is
defined. End Receipt Period The end date of the period that the items, for which you send
the request for quotation, are scheduled to be delivered. Default value LN retrieves the default end date from the Requests for Quotation Overview (tdpur1501m000) session. Note The end date is copied to the purchase order or purchase
contract when you copy the RFQ line in the Convert RFQs (tdpur1202m000) session. This happens
after you accept the RFQ response from the bidder. You cannot define a delivery period if a delivery date is
defined. Lead Time When you manually specify the request for quotation (RFQ), you
can define a lead time that will be used on the purchase order to determine the
delivery date. Delivery date = order date + lead time. Lead Time Unit The unit in which the lead time is expressed. Project The project to which the
item on the request for quotation (RFQ) line is related. Note If the RFQ line represents a customized item, the project
in this field must be equal to the project as specified in the project segment
of the Item field. You can also send an RFQ for standard items that are
related to a specific project. In this case, you can specify a project in the
current field. Element The smallest part of an element structure. An element is used
to define the (structure of the) work of the project, so that you can carry it
out. Activity The smallest part of the activity structure used for a
time-scaled budget. An entity that is used to represent a part of a project in
an activity structure. LN distinguishes these activity types: - WBS Element
- Control Account
- Work Package
- Planning Package
- Milestone
Extension The specific agreements within or in addition to the initial
contract. An extension falls outside the initial contract with the sold-to
business partner. Extensions can be assigned to the bottom-up
budget. LN distinguishes four extension types: - Scope Change
- Provisional Amount
- Fluctuation Settlement
- Quantities to be Settled
Cost Component A cost component is a user-defined category for the
classification of costs. Cost components have the following functions: - To break down an item's standard cost, sales price, or
valuation price.
- To create a comparison between the estimated production order
costs and the actual production order costs.
- To calculate production variances.
- To view the distribution of your costs over the various cost
components in the Cost Accounting module.
Cost components can be of the following cost types: - Material Costs
- Operation Costs
- Surcharge on Material Costs
- Surcharge on Operation Costs
- WIP Transfer Costs
- General Costs
Note If you use Assembly Control (ASC), you cannot use cost components
of the General Costs type. Subject to Trade Compliance If this check box is selected, global trade compliance applies to the line. Note This field is available only if the Import Compliance check box is selected in the Global Trade Compliance Parameters (tcgtc0100m000) session. Peg Distribution If this check box is selected, a peg distribution is linked to this RFQ Line. MandatoryProject Peg If this check box is selected, the item must be pegged
to a project, which means the item must have a linked peg. Default value The Mandatory Project Peg check box in the Items (tcibd0501m000) session. Score Date The date on which the last response score is calculated for the RFQ
line. Score Actual If this check box is selected, the calculated response score for the RFQ line is actual and is used
when comparing response lines in the RFQ Compare Responses (tdpur1600m100) session. If this check box is cleared, the calculated response
score for the RFQ line is no longer applicable, for example, because values
have changed in the RFQ Responses (tdpur1506m000) session. Consequently,
when the RFQ Compare Responses (tdpur1600m100) session is accessed, the response score is
recalculated. Line Text If this check box is selected, a text is present. | |