| To create parts per million chartsThis chart is used to compare the actual Parts per Million (PPM)
quality performance of an item against a target and mean measurement (for a
month/year). The chart is drawn from the actual inspection results for a user
defined period. The part per million charts is created based on the data in
the Item Quality Statistics (qmptc1140m000) session. Example: The chart is plotted, based on the following
rules: - PPM values are determined for every order origin, item or
item/supplier, year and period.
- Assume that every unit of an inspected item is an
opportunity.
- Determine the total number of units inspected in the period,
that is, the total opportunities per period.
- Determine the total numbers of units rejected in the period,
that is, the total defect per period.
- Defects per Opportunity represents the number of defects
divided by the number of opportunities in the period. Defects per
Opportunity per Period = Total Defects per period Total Opportunities per
period.
- Defects per Million Opportunities represents the defects per
period times a million. Defects per million Opportunities per month =
Defects per Opportunity per month x 1000000
- Defects per Million per Year is similarly calculated using
the total number of opportunities and the total number of defects in the
year.
- The calculated data of Defects per Million Opportunities per
period is displayed. Each period is represented by an individual point on the
chart.
- The Defects per Million Opportunities per year can be plotted
as a calculated mean across all periods in the year or for each
quarter.
How it works in LN You can access the PPM chart from the Item Quality Statistics (qmptc1140m000) session. The chart is created for the
display fields in the session, for all the periods of the selected year. When
multiple periods are selected, the range is extended based on the
selection. Note If you select periods 3 and 5, period 4 is also displayed
to maintain consistency. When the chart is initially started, the defaults are saved
in the Parts Per Million Chart (qmptc1740m000) session. Click Modify Chart to change
the values. The following are the options to modify the PPM
chart: Include Skip Lot Accepts: This flag determines if accepted batches for skipped order
inspections must be included in the data used to generate the
chart. Re-Inspection: Use the Excluding Re-Inspection and Including Re-Inspection
options to determine the data used to generate the chart. The following example
describes how data is plotted in the chart for the selected option. Example The following orders are defined for a period: Unit | Sample | Characteristic
1 | Characteristic 2 | Characteristic
3 | Result | 1 | 1
unit | Pass | Fail | Fail | 1 sample
failed | 2 | 1
unit | Pass | Pass | Pass | 1 sample
passed | 3 | 1
unit | Fail | Fail | Fail | 1 sample
failed | 4-5000 | 4996
units | Pass | Pass | Pass | 4996 samples
passed |
- The result is 2 failures out of a sample of 5000 or 2/5000
*1,000,000 or 400 ppm.
Order Inspection | Order
Quantity | Sample Quantity | Accepted /
Rejected | Re-inspection
Order | 1 | 100 | 100 | Accepted | | 2 | 200 | 200 | Rejected | 3 | 3 | 200 | 200 | Rejected | | 4 | 200 | 200 | Rejected | | 5 | 200 | 200 | Accepted | | 6 | 200 | 200 | Rejected | 7 | 7 | 200 | 200 | Rejected | 8 | 8 | 200 | 200 | Accepted | |
The cumulative results are: - Quantity Accepted excluding Re-Inspection: 300 (order 1 and
5).
- Quantity Rejected excluding Re-Inspection: 600 (order 2, 4
and 6).
- Quantity Accepted including Re-Inspection: 500 (order 1, 5
and 8).
- Quantity Rejected including Re-Inspection: 400 (order 3 and
4).
The results are displayed in the Item Quality Statistics (qmptc1140m000) session: Accepted excluding
re-inspection | Rejected excluding re-inspection | Accepted
including re-inspection | Rejected including
re-inspection | Quantity
skipped | 300 | 600 | 500 | 400 | 0 |
If you select the Exclude Re-Inspection option, the data
on the chart is plotted as: - Accepted - 300
- Rejected - 600
If you select to Include Re-Inspection option, the data on
the chart is plotted as: - Accepted - 500
- Rejected - 400
| |