Production Orders (tisfc0501m000)

Use this session to maintain or display the production orders used in LN.

Production orders go through a number of order statuses, for example:

  • Created
  • Printed
  • Released

The order status determines which actions can be performed on a production order. For more information, refer to Production order status.

Header-lines session

Double-click a record in the Production Orders (tisfc0501m000) session to start the Production Order (tisfc0101m100) header-lines session. In this session, you can carry out tasks that relate to the material side and the operations side of a production order. LN not only displays general data and planning data such as the planning method, production start date, and the planned delivery date, but also other data related to a particular production order by means of the following tabs:

Performance aspects

The settings in this session could affect system performance and database growth. For more information, refer to Production order without operations and Archive and delete in Job Shop Control.

 

Production Order

The production order for which the data is recorded.

Item

The item produced by the production order.

Quantity Ordered

The quantity to be produced by the production order.

Planned Delivery Date

The date when you plan to deliver the item produced by the production order.

Order Status

The order status of the production order.

Allowed values

Order Status

Warehouse

The warehouse where the items produced by the production order are stored.

You can change this warehouse in the Warehouse field of the Production Order (tisfc0101m100) session, unless deliveries have already been made.

Requested Delivery

The date that the customer has requested for the production order.

  • If the planning method is Forward, the Requested Delivery Date equals the Planned Delivery Date of the moment the production order is generated.
  • If the planning method is Backward, the Requested Delivery Date is the starting point for planning.
Production Start

The date and time on which the order is planned to be taken into production. The Production Start field is filled during production order creation. If the production planning changes, this date can be automatically updated.

The start date of the order can be copied from the planned orders generated in the modules:

  • Warehouse Orders
  • Inventory Planning
  • Order Planning

Forward planning If the planning method field has the value Forward, the production start date can be used to calculate the delivery date.

Backward planning If the planning method field has the value Backward, the production start date can be derived from the delivery date and the order lead time of the item. The production start date is then calculated as follows: Production start date = delivery date - order lead time of item This formula is used in the following situations:

  • When you manually enter a production order
  • When you click the Plan button to recalculate the production start date
  • When a production order for an item of type Manufactured or Product has no routing and is transferred to the Job Shop Control module.
Definitively Closed

If this check box is selected, all financial transactions for the production order are deleted by the Delete Production Order Transactions (ticst3200m000) session. You cannot reset the production order status anymore.

Priority

The priority of an order determines the print sequence in the Print Production Order Planning by Priority (tisfc1410m000) session. Tools are returned to the orders with the highest priority. The highest priority is indicated by 1, the lowest by 999.

Planner

The employee responsible for planning the production order.

Shop Floor Planner

The person responsible for printing, (re)scheduling and releasing production orders and managing workloads.

Revision

The revision of the item.

Allowed values

A revision can only be entered if the item is a revision-controlled engineering item and the Engineering Revisions Active check box in the Production Order Parameters (tisfc0100s000) session has been selected.

Default value

The default for this field is the current revision.

You must enter a valid revision that has been defined for the item in the Engineering Data Management module.

Note

Once you have started issuing the material, you cannot change this field any longer.

Text

If this check box is selected, a text is present for the production order you selected.

If a text is present for a production order, you can click the Start Text Editor icon on the toolbar to change the text.

Click the Start the Text Editor icon on the toolbar of the Production Order (tisfc0101s000) session, to write the initial text for a production order.

Contains Customer Furnished Material

If this check box is selected, the production order contains customer furnished material.

Sold-to Business Partner

If an order is a sales order this field displays the business partner it is sold to.

Specification

If this check box is selected, a specification is present for the material. From the appropriate menu, click Specification to start the Specification (tcibd4120m000) session. In this session you can view the applicable specifications.

Sold-to Business Partner

The supply that fills this demand must have been allocated or demand pegged to the sold-to business partner displayed in this field.

LN uses this characteristic to find a matching supply for this demand.

Business Object Type

The supply that fills this demand must have been allocated or demand pegged to the type of order displayed in this field.

LN uses this characteristic to find a matching supply for this demand.

Note

The following fields are always used in combination; together, they identify the relevant order or order line:

  • Business Object Type
  • Business Object
  • Business Object Reference
Business Object

The supply that fills this demand must have been allocated or demand pegged to the order, or order line, displayed in this field.

LN uses this characteristic to find a matching supply for this demand.

Note

The following fields are always used in combination; together, they identify the relevant order or order line:

  • Business Object Type
  • Business Object
  • Business Object Reference
Business Object Reference

The supply that fills this demand must have been allocated or demand pegged to the type of order displayed in this field.

LN uses this characteristic to find a matching supply for this demand.

Note

The following fields are always used in combination; together, they identify the relevant order or order line:

  • Business Object Type
  • Business Object
  • Business Object Reference
Reference

The supply that fills this demand must have been allocated or demand pegged to the reference code displayed in this field. LN uses this characteristic to find a matching supply for this demand.

LN can use this field in two ways:

  • If the Sold-to Business Partner field is filled, LN uses the Reference field to record a reference code defined by a customer.
  • If the Sold-to Business Partner field is empty, LN uses the Reference field to record an internal reference.

You can use a reference code to keep a collection of parts linked together, even if they follow different routings, for example, if some of the parts are transported to a subcontractor to be returned later.

Production Order Group

The order group to which the production order belongs.

Related topics

Version

The production order version ID.

Note

The Version Control check box in the Production Order Parameters (tisfc0100s000) session must be selected.

Project (PCS)

The project for which the production order is intended.

If this field is empty, the product of the production order is an anonymous item.

Routing

The routing for the production of the item. If no routing is entered, there are no estimated production costs defined for the production order.

Default value

The default routing is based on the Default Routing field in the Routing Parameters (tirou0100m000) session unless order quantity dependent routings are used.

Reference Date

This date determines the selection of operation lines and BOM lines defined in the sessions:

Planning Method

If the Planning Method field is Forward, the delivery date is planned forward based on the Production Start field.

If the Planning Method field is Backward, the production start date is planned backward based on the Planned Delivery field.

You can only alter this field for:

  • Manually-entered orders
  • Orders transferred from the Warehousing package.
Confirmed Delivery

The production delivery date of the order confirmed to the customer by, for example, the job shop planner. You can manually alter this date, until the production order is completed.

Distribution Type

View the distribution type for the materials to be issued.

Allowed values

Distribution Type

Operations Present

If this check box is selected, the production order has at least one operation.

Operations Blocked

If this check box is selected, at least one of the operations of the production order has been blocked.

Related topics

Rework Order

If this check box is selected, the production order is a rework order.

The rework order can have one of these origins:

  • Manual
  • Quarantine to existing specifications
  • Quarantine to new specifications
  • Refurbish Tool

Related topics

Print Label during Report Orders Completed

If this check box is selected, a label is printed for this production order when you use the Report Orders Completed (tisfc0520m000) session to report the production order as complete.

Routing Group

A group of items with similar routing attributes, for example, the same work center, routing operation, BOM, and so on. A routing group is defined by the user as a selection criterion for production orders.

Actual Production Start Date

The actual date when work on the production order was started.

Actual Delivery Date

The date and time when the order was delivered.

Previous Operation(s)

This field determines the effect of operation rescheduling on the planning of preceding operations.

Default value

The default for this field is the Moving Method Previous Operations field in the Default Production Order Data (tisfc0102m000) session.

Moving Method Next Operations

This field determines the effect of operation rescheduling on the planning of follow-up operations. The value in this field is the default value for the Subsequent Operations field in the Production Orders (tisfc0501m000) details session.

When moving operation 30 of the following operation structure, operations 40, 50, and 60 are affected by the moving method next operation field:

[...]

The moving method for operations is not taken into consideration when shifting the production planning by means of the Production Orders (tisfc0501m000) session or the Shift Production Planning (tisfc1202m000) session. The moving method is only used when shifting on the operation level in the Production Planning (tisfc0110m000) details session.

Allowed values

Possible Values

Quantity Initial

The order quantity for the effectivity unit at the time the production order was released.

Quantity to Deliver

The cumulative value of the part of the production order that is waiting to be delivered to inventory.

When Warehousing finishes the inbound procedure for the delivered items, LN adds the value of the Quantity to Deliver field to the Delivered field, and sets the Quantity to Deliver field back to zero.

Quantity Delivered

The quantity of finished goods posted to inventory.

Scrapped

The quantity of the item produced by the production order that was scrapped. This quantity can no longer be reworked or used for any purpose.

Quantity Quarantined

The quantity that is quarantined.

Reason for Rejects

The reason for the rejection. Use a reason with reason type Rejection of Production Result.

To define the reasons for rejection, use the Reasons (tcmcs0105m000) session.

Receipt Inspection Required

If this check box is selected, an inspection of the items is required upon receipt of the finished quantity in the warehouse.

Backflush Materials

If this check box is selected, the materials for the production order are issued through backflushing.

Serialized items can only be backflushed if in the Items - Warehousing (whwmd4500m000) details session the Serials in Inventory check box is cleared, and the Register Serial Issue During As Built field is Yes. In all other cases, serialized items cannot be backflushed.

If the serialized item is lot-controlled, the lot from which the items are backflushed is based on the outbound method ( Last In First Out (LIFO), First In First Out (FIFO)) as is defined in the Items - Warehousing (whwmd4500m000) details session.

Backflush Hours

If this check box is selected, you can backflush the hours spent to manufacture the item to the related employee.

Related topics

Quantity to Backflush

The quantity that still has to be backflushed.

Quantity Backflushed

The quantity already backflushed.

Calculation Office

A work center of the type Costing that is used to determine the enterprise unit for a project, or production order and also has an administrative function.

Note

When linked to production orders, the Use as Calculation Office check box in the Work Centers (tirou0101m000) session must be selected for the work center.

Split Hours in Setup and Production

If this check box is selected, the estimated and actual hours of an operation are split up.

The estimated and actual hours of an operation can be split up in setup time hours and cycle time hours. This results in a setup part and a production part for the estimated and the actual man and machine hours, which can be viewed in, for example, the Estimated vs. Actual Hours Costs (ticst0502m000) session.

Note

Selecting this check box can negatively impact system performance if hours are backflushed. Hours are backflushed if the Backflush Hours check box in the Item - Production (tiipd0101m000) session is selected.

WIP Transfer Cost Component

The cost component on which WIP transfers between work centers are posted.

The cost component must be of the type Obsolete. If the Financial Transactions by Work Center check box in the Production Order Parameters (tisfc0100s000) session is cleared, the WIP Transfer Cost Component field may stay empty.

This field cannot be changed after the estimates are frozen or the first WIP transfer is executed.

Moment Freezing Estimates

The moment when LN freezes the estimated order costs. When the estimated order costs have been frozen, you can no longer modify the data in the Estimated Materials (ticst0101m000) session.

Note
  • This field applies only when the Version Control check box is cleared in the Production Order Parameters (tisfc0100s000) session.
  • The value in this field is the default value for the Moment Freezing Estimates field in the Production Orders (tisfc0501m000) details session.

Performance aspects

The setting of this field could affect system performance and database growth. For more information, refer to Moment of freezing estimates.

Allowed values

Possible Values

Moment of Completion Posting

The moment when LN posts the financial transactions for the completed quantities to Financials.

For more information, see Moment of Completion Posting.

Calculation Date

The date on which the calculation of the estimated end item unit costs is based.

The date in the Calculation Date field in the Production Orders (tisfc0501m000) session is not necessarily the date when the calculation is performed, because you can define in the Calculate Estimated End Item Unit Costs (ticst0210m000) session another date than the current date for the calculation.

Note
Closing

The date and time when the production order was closed.

Financial Transactions by Work Center

If this check box is selected, you can view the production results by work center. The default setting is determined by the Financial Transactions by Work Center checkbox in the Production Order Parameters (tisfc0100s000) session.

Estimated Costs Are Frozen

If this check box is selected, the estimated end item unit costs have been frozen, which means they can no longer be modified.

The moment the estimated end item unit costs are frozen depends on the Moment Freezing Estimates field.

Actual WIP Transaction Done

If this check box is selected, a WIP transaction has been done, which means the order status has become Active.

End Item Receipt Posting

If this check box is selected, end items are received in inventory at their actual costs, and valued according to the defined actual valuation method.

Note

Calculation-office variances can occur for JSC orders with project pegs if planned project pegs deviate from the actual project pegs of the end item. These variances cannot be attributed to price or efficiency.

If this check box is cleared, FTP inventory valuation method is used.

Performance aspects

The setting of this field could affect system performance and database growth. For more information, refer to Actual cost for receipt posting.

Use Actual Valuation for WIP Transfers

If this check box is selected, the financial transactions of the type WIP Transfer Issue, WIP Transfer Receipt and Completion are logged against actual costs.

Use Actual Valuation for Subassembly Receipt Posting

If this check box is selected, subassemblies are received in inventory at their actual costs, and valued according to the defined actual valuation method.

Valuation methods are defined in Warehousing.

The actual valuation methods are:

  • Moving Average Unit Cost (MAUC)
  • First In First Out (FIFO)
  • Last In First Out (LIFO)
  • Lot Price (Lot)
Parent Order

The production order number of the parent order.

Note

If this field is specified, this is a child production order that originates from a split order.

Order Split Applied

If this check box is selected, the production order is split off into one or more child orders.

Inspection Note Printed

If this check box is selected, the inspection note for the production order was printed.

Allowed values

Possible Values

Related topics

Covering Note Printed

If this check box is selected, the covering note for the production order was printed.

Allowed values

Possible Values

Related topics

Routing Sheet Printed

If this check box is selected, the routing sheet for the production order was printed.

Allowed values

Possible Values

Related topics

Operation Note Printed

If this check box is selected, the operation note for the production order was printed.

Allowed values

Possible Values

Related topics

Material List Printed

If this check box is selected, the material list for the production order was printed.

Allowed values

Possible Values

Related topics

Material Issue Note Printed

If this check box is selected, the material issue note for the production order was printed.

Allowed values

Possible Values

Related topics

Subcontracting Note Printed

If this check box is selected, the subcontracting note for the production order was printed.

Allowed values

Possible Values

Related topics

Checklist Printed

If this check box is selected, the checklist for the production order was printed.

Allowed values

Possible Values

Related topics

Sawing List Printed

If this check box is selected, the sawing list for the production order was printed.

Allowed values

Possible Values

Related topics

Cutting List Printed

If this check box is selected, the cutting list for this production order was printed.

Allowed values

Possible Values

Related topics

Receipt Note Printed

If this check box is selected, the receipt note for the production order was printed.

Allowed values

Possible Values

Related topics

Serial Number List Printed

If this check box is selected, the serial number list for the production order was printed.

Allowed values

Possible Values

Related topics

Order Distribution Printed

If this check box is selected, the order distribution for the production order was printed.

Allowed values

Possible Values

Related topics

Subcontracting with Material Flow

If this check box is selected, subcontracting with material flow is supported for the end items of this production order.

Note

During creation of the production order, the value of this check box is defaulted from the Subcontracting with Material Flow check box in the Item - Production (tiipd0101m000) session. After order creation, you can no longer change the setting of this check box on the production order.

First Article Inspection

If this check box is selected, a first article inspection is performed once a quantity of the production order is completed.

Note

This check box is only visible if the Quality Management (QM) check box is selected in the Implemented Software Components (tccom0100s000) session.

First article inspection is triggered for a production order, when the rules are defined for the main item of the production order in the First Article Inspection (qmptc2150m900) session.

Standard Inspection Orders

If this check box is selected, an inspection order is linked to the production order.

 

Micro Routing

Click to start sessions that have to do with the microrouting.

Production Planning

Click to start sessions that have to do with production planning.

Materials

Click to start sessions that have to do with material.

End Item

Click to start the sessions that have to do with the end item.

Costs

Click to start sessions that have to do with production order costing.

Exception Handling

Click to start sessions that restart, reset, or reprocess production orders.

Shift Production Planning

Click to start the Shift Production Planning (tisfc1202m000) session in which you can shift the production planning forward or backward.

If you shift the production planning forward, you create a delay, which you can use, for example, to cope with a backlog in production.

You can only use the Shift Production Planning (tisfc1202m000) session for production orders with the following order status:

  • Created
  • Printed
  • Released
Blocked Operations

Click to start the Blocked Operations (tisfc0540m000) session in which LN displays the operations that you manually blocked, together with the reasons for blocking the operations.

In the Report Operations Completed (tisfc0130m000) session you can unblock the routing operations you blocked previously, or change the blocking reason.

Show All Orders

Click to view all existing production orders.

Show Orders In Use

Click to display the production orders with the following status:

  • Created
  • Scheduled
  • Printed
  • Released
  • Active
  • Production Completed
Pegging - Downstream/Upstream

Click Pegging - Upstream to start the GBF browser in which you can view the production order's supply orders, that is, the preceding production orders and/or purchase orders.

Click Pegging - Downstream to view the production order's demand orders, that is, the successive production orders and/or sales orders.

You can only start pegging if the following is true:

For more information, refer to Pegging for planned orders.

Generate Alternatives for Estimated Materials
Set Status to Scheduled

If you usually process production orders with Infor SCM Scheduler, click this option if you want to manually bypass Infor SCM Scheduler. The production order status is then set from Created to Scheduled. You can continue the normal production order procedure in LN. A reason to bypass Infor SCM Scheduler is, for example, in case of rush orders, when you have no time to perform the usual scheduling run in Infor SCM Scheduler.

Note that you can only see this option if Infor SCM Scheduler is installed, and the Infor SCM Scheduler check box in the Implemented Software Components (tccom0500m000) details session is selected.

Note that, unlike Infor SCM Scheduler, LN assumes infinite capacity during scheduling. As a result, capacity problems can occur. You must then run Infor SCM Scheduler to solve those problems.

Specification