| Activity Overview by Project (tipcs4502m000)Use this session to display the activity
list by project. Project A collection of manufacturing and purchasing actions that are
performed especially for a particular customer order. A project is initiated to
plan and coordinate the production of these items. For a standard-to-order production, the project is only
used to link the item with the customer order. Otherwise, a project can
include: - Customized item data (BOMs and routings)
- Project planning (activity planning)
Project Status Indicates the current progress of the project. Activity This code identifies an activity in the network planning for a
project. Search Key An alternative form of a description used for convenience
during searching. Typically, it is an abbreviation, an acronym, or a mnemonic
alternative to a full description. Task LN shows
the number of the task linked to the activity. The task number
gives more detailed information about the activity. ActivityManager A person responsible for planning or carrying out a project
activity. Text This field shows whether or not a text is present. Capacity Load Table A table in which you can define how the rough capacity
requirements are to be distributed over the capacity duration. The x coordinate
is a percentage of the activity duration. The y coordinate is a percentage of
rough capacity requirements. RoughCapacity The globally needed capacity in hours for the execution of the
relevant activity. AggregatedCapacity The aggregated capacity requirements in hours of the work
center where the activity is scheduled to be carried out. The aggregated
capacity requirements are calculated in the Aggregate Estimated Capacity to Project (tipcs4201m000) session on the basis of the
project structure and the project engineering. You can only do this if the
operations have been linked to activities in the customized routing. Dependent
on the value of the Critical Capacity for Planning field in the Work Centers (tirou0101m000) session, Man Capacity or Machine Capacity is used to calculate the aggregated capacity. The aggregated
capacity requirements are only shown for your information and can be used for
checking or monitoring the rough planned hours by activity. AverageCapacity Enter the available capacity in hours per day. This capacity is
used to calculate the default activity duration. The planning factor enables
you to record the available capacity in hours per day for each employee or
machine. Based on this capacity, LN calculates the default
duration of an activity using the appropriate formula: Default acitivity duration = Rourh capacity requirement /
(Planning factor x Available Capacity) PlanningFactor The planning factor indicates how many employees or machines
are employed simultaneously for the execution of an activity. This factor is
used only to calculate the default duration of the activity on the basis of the
global capacity requirements and the available hours per day. LeadTime The time between the production start date and the delivery
date. The lead time can include order preparation time, transportation time,
and inspection time. Latest Start Date The last date on which the activity can be started. Determine
this date by using the Generate Network Planning (tipcs4210m000) session. Earliest End Date Rhe earliest date on which the activity can be completed.
Determine this date using the Generate Network Planning (tipcs4210m000) session. LatestEnd Date The last date on which the activity can be completed. Determine
this day using the Generate Network Planning (tipcs4210m000) session. TotalFloat The total float of an activity is the maximum time expressed in
(working) days in which that activity can be shifted without affecting the
planned completion date of the relevant project. The total float-time
is calculated as follows: Total Float = Latest
Finish - Earliest Start - Activity Duration The latest finish
date and earliest start date are expressed in project days. Note The corresponding Total Slack field in MS Project is
expressed in hours. The conversion is based on the Work Center field and the Basic Day Capacity[Hours] field linked to the
specified work center. FreeFloat The free float time between one activity and the next. The free
float time indicates how many days the activity can be extended without
jeopardizing the progress of other related activities. Note The corresponding Free Slack field in MS Project is
expressed in hours. The conversion is based on the Work Center field and the Basic Day Capacity[Hours] field linked to the
specified work center. Desired Start Date The date on which you want to start the relevant activity. This
date is only used for information. However, the desired start date is compared
to the earliest and latest finish dates and the reference date in the Generate Network Messages (tipcs4211m000) session. This can result in the creation of
exception messages. DesiredFinish Date The date on which you want to stop the execution of the
relevant activity. This date is only used for information. However, the desired
finish date is compared to the earliest and latest finish date and the
reference date via the session Generate Network Messages (tipcs4211m000), which can result in the creation of
exception messages. MakeEstimate Indicates whether the relevant activity must be included in the
estimated cost-price calculation for the project. This can be especially
important for indirect activities, such as engineering. Low LevelCode The Low Level code indicates the lowest level at which the
activity is found in the activity network for the project. This code is
determined by the Generate Network Planning (tipcs4210m000) session. Actual Start Date The actual start date for the activity is the date on which its
execution was started. LN fills the actual start date, when transaction hours are processed with the Process Hours and Expenses (bptmm1203m000) session, or when a network calculation is
executed using the Generate Network Planning (tipcs4210m000) session. You can change this date manually. Actual End Date The actual finish date for the activity is the date on which
time was last spent on or on which the activity was completed. LN fills the actual
finish date, when transaction hours are processed with the Process Hours and Expenses (bptmm1203m000) session, or when a network calculation is
executed using the Generate Network Planning (tipcs4210m000) session. You can change this date manually. Spent Critical Capacity The actual hours spent on the relevant activity. Based on the
hours transactions linked to the activity, LN automatically updates
this value in the Process Hours and Expenses (bptmm1203m000) session. PercentageCompleted The percentage completed shows the activity's progress. Note Because of the
non-linear distribution of capacity-requirements, the percentage completed is
not related to the lead-time but to the global capacity-requirements. If you
choose an automatic calculation of the percentage completed, this percentage is
determined on the basis of the global capacity-requirements and the actual
hours spent. AutomaticUpdate This field indicates whether the percentage completed must be
automatically determined using either the Process Hours and Expenses (bptmm1203m000) session when transaction hours are processed,
or the Generate Network Planning (tipcs4210m000) session when a network calculation is
executed for the project. | |