Transferring orders to execution levelYou use the Plan Transfer module to transfer planned orders from Enterprise Planning to the execution level of LN. In addition, it allows you to transfer production plans and purchase plans. General Procedure Step 1. Origin of transferred orders You can transfer orders from the actual scenario only. The following types of planned supply can be transferred: Step 2. Destination of transferred orders
Step 3. Planned materials If you transfer planned production orders to the Job Shop Control module, LN will respect the material selections and quantities as planned by the Enterprise Planning package. Step 4. Order Status As a rule, LN only transfers planned orders with Confirmed order status. However, on the Options tab in the Transfer Order Planning (cppat1210m000) session, you can change the session's behavior:
Step 5. Workload-based transfer When you transfer production orders, you can set a maximum to the total workload that will be transferred to a resource. See: Workload-based order transfer. Step 6. Order grouping You can use the order-grouping functionality in the Plan Transfer module to group planned production orders according to various criteria. You can use this functionality to transfer a whole order group at once, and (optionally) translate it to an JSC order group. Step 7. Order release For some planned orders, the Order Release field in the Planned Orders (cprrp1100m000) session is Not to be released. You cannot transfer these planned orders to the execution level, until the Order Release field is set to To be released. These planned orders are used in a vendor managed inventory (VMI) setup.
| |||