For a standard-to-order production, the project is only used to link the item with the customer order. Otherwise, a project can include:
- Customized item data (BOMs and routings)
- Project planning (activity planning)
Confirm and Post Interim COGS and Revenues by Project (tipcs3291m000)Use this session to confirm the interim COGS and revenue for a specific PCS project, and post them to the General Ledger (GLD) module in Financials. Interim COGS and revenue for a PCS project are useful when you want to gain an insight into the interim results of a PCS project, even before any end item is shipped. After you run the Calculate Interim COGS and Revenues by Project (tipcs3290m000) session, the aggregated COGS and revenue of a specific PCS project can be viewed and maintained in the Interim COGS and Revenues by Project (tipcs3190m000) session. After you have viewed and maintained the interim COGS and revenue, you must confirm and post them to the General Ledger (GLD) module in Financials:
Project A collection of manufacturing and purchasing actions that are
performed especially for a particular customer order. A project is initiated to
plan and coordinate the production of these items. For a standard-to-order production, the project is only used to link the item with the customer order. Otherwise, a project can include:
Project Status The status assigned to a PCS project, which indicates how far
the project has been processed. Project Employee The person who is in charge of the project. Calculation Office A work center of the type Costing that is used to determine the enterprise unit for a project, or production
order and also has an administrative function. Calculation Group A code representing a group of projects the user uses to
compare financial data. You can assign a calculation group to:
Search Key An alternative form of a description used for convenience
during searching. Typically, it is an abbreviation, an acronym, or a mnemonic
alternative to a full description. End Date The date until which the actual costs are taken into account
for revenue recognition. The date is determined in the Calculate Interim COGS and Revenues by Project (tipcs3290m000) session when calculating
interim revenue and COGS. Confirm Interim COGS and Revenues If this check box is selected, and you run the Confirm and Post Interim COGS and Revenues by Project (tipcs3291m000) session, the
interim COGS and revenues are confirmed. After confirming, you cannot adjust
data in the Interim COGS and Revenues by Project (tipcs3190m000) session anymore. Note You can also confirm the interim COGS and revenue by clicking (de-) Confirm in the Interim COGS and Revenues by Project (tipcs3190m000) session. You can deconfirm the data by clicking (de-) Confirm again. Post Interim COGS and Revenues If this check box is selected, and you run the Confirm and Post Interim COGS and Revenues by Project (tipcs3291m000) session. The
interim COGS and revenue for the PCS project is posted to the General Ledger (GLD) module in Financials. Posting Date Cost/Turnover Sales The date that the interim COGS and revenue are posted to the General Ledger (GLD) module in Financials.
| |||