Allowed values
- Import: The XML file is imported.
- Export: The XML file is exported.
External Scheduling Interface (tppss2231m000)Use this session to export a project to an external scheduling package, such as Microsoft Project, using an XML file and to import the scheduling information back to Infor LN (after optimizing the project planning in the external scheduling package).
Note The values in the Activity Code Custom Field Text, Activity Description Custom Field Text, and Activity Primary Key Custom Field Text field must be different. Note You can view the fields in the Options tab and the Selection tab only if the Selection field is set to Single Project.
Selection Action Export/Import The direction of flow of the XML files. Allowed values
Selection Selection Indicate whether a single project or multiple projects must
be imported from/ exported to an external scheduling package. Allowed values
Note You can link only one project to an XML file. Infor LN sets this field to Single Project, if the Multiple Import/Export check box is cleared in the Project Selection (tppss2140m000) session. Export Project The code that uniquely identifies the project. Note This field is enabled only if the Export/Import field is set to Export. Description The description or name of the code. Connection Node The activity or node of the Infor LN Project that
must be connected to the activity or node of a project in the external
scheduling package. If you link a complete project in Infor LN to a
project in the external scheduling package, this node is not
specified. For example, if a project planner manages all the engineering activities in the office and another planner manages all the onsite construction activities. You can split the project accordingly and each planner can control their respective responsibilities to optimize the project. The application also allows each planner to use a different external scheduling package. Note To select an activity as the connection node, these are the constraints:
XML path The path of the XML file that is exported. This field is
displayed based on the type of user interface that is used. Note This field is enabled only if the Export/Import field is set to Import. XML file The name of the XML file that is exported. Note This field is enabled only if the Export/Import field is set to Import. Start Application If this check box is selected, LN starts the external schedule package application, after the XML
has been created. This field is displayed based on the type of user interface
that is used. Note This field is enabled only if the Export/Import field is set to Export. Application Starts the external schedule package application. This
field is displayed based on the type of user interface that is used Note This field is enabled only if the Start Application check box is selected and if the Export/Import field is set to Export. Import Project The code that uniquely identifies the project. Note This field is enabled only if the Export/Import field is set to Import. Description The description or name of the code. XML path The path of the XML file that is exported. This field is
displayed based on the type of user interface that is used. Note This field is enabled only if the Export/Import field is set to Import. XML file The name of the XML file that is exported. Note This field is enabled only if the Export/Import field is set to Import. Project Number Group The number group of the project. This is a display field. Series The first free numbers of the project linked to the imported
XML file. Note
However, the application does not support all possible scenarios. For example, the series or task codes in a XML file can be more than the 16 characters but the file cannot be successfully imported. This is because LN limits the number of characters that can be used for a series code to 16 characters. Project Management Office The project management office to be used when a new project is created in
LN. Description The description or name of the code. Enterprise Unit The enterprise unit of the project linked to the imported XML file. Note This field is enabled only if the Export/Import field is set to Import. You must specify the enterprise unit in this field when a new project must be created. Planning Regenerate XML file If this check box is selected, LN regenerates the XML file. Note Information entered in an External Scheduling Package and stored in an XML file but not stored in LN could be lost. You can view this field only if the Selection field is set to Single Project. This field is enabled only if the Action field is set to Export. Use LN Calendars If this check box is selected, Infor LN calendar
data is exported to the external scheduling interface and you can perform the
planning using the calendars in the external scheduling package (ESP). It is
recommended to use this option, since Infor LN uses these
calendars as well. If this check box is cleared, Infor LN calendar data is not exported to the external scheduling interface. Effectively, the size of the calendar data in the exported XML file is reduced. Planning date and the duration are scheduled in the external scheduling package (ESP), based on the external scheduling package (ESP) calendar. Note By default, this check box is selected. This field is enabled only if the Regenerate XML file check box is selected. You can view this field only if the Selection field is set to Single Project. Calendar The code of the calendar that you want to make available to
external scheduling packages. Note Infor LN defaults this value from the following sessions based on this priority sequence:
Description The description or name of the code. Availability Type The default availability type that the
external scheduling package uses. Note This value is defaulted from the Calendar Parameters (tcccp0100m000) session. Description The description or name of the code. Procedure Show Warnings If this check box is selected, LN displays warning messages when there is an error in executing the
integration the process. Status The status of the XML file when you import/ export to an
integration external schedule package. Status The description of the status. Options Transfer Resource Material If this check box is selected, LN exports the material cost objects (including price, hours and
quantity) of the project to an external schedule package. Note This field affects the performance of the CPU and the database growth if several resources are transferred. Labor If this check box is selected, LN exports the labor cost objects (including price, hours and
quantity) of the project to an external schedule package. Employees If this check box is selected, LN exports only the employee labor cost objects (including price,
hours and quantity) of the project to an external schedule package. Trade Group If this check box is selected, LN exports only the trade group labor cost objects (including price,
hours and quantity) of the project to an external schedule package. Labor Cost Object If this check box is selected, LN exports all labor cost objects (including price, hours and
quantity) of the project to an external schedule package. Equipment If this check box is selected, LN exports the equipment cost objects (including price, hours and
quantity) of the project to an external schedule package. Subcontracting If this check box is selected, LN exports the subcontracting cost (including price, hours and
quantity) of the project to an external schedule package. Sundry Cost If this check box is selected, LN exports the sundry costs of the project to an external schedule
package. Transfer Assignment Material The assignment level of material cost objects (resources)
exported to the activities/budget lines (tasks) of the external schedule
package. Allowed values Labor The assignment level of labor cost objects (resources)
exported to the activities/budget lines (tasks) of the external schedule
package. Allowed values Equipment The assignment level of equipment cost objects (resources)
exported to the activities/budget lines (tasks) of the external schedule
package. Allowed values Subcontracting The assignment level of subcontracting cost objects
(resources) exported to the activities/budget lines (tasks) of the external
schedule package. Allowed values Sundry Cost The assignment level of sundry costs to be exported to an
external schedule package. Allowed values Task Task name based on The activity related data on which the task name of the ESP
is based. Allowed values Note Default value is Code. This field is enabled only for the new imports/ exports, and exports that are regenerated. You can view this field only if the Selection field is set to Single Project. For import related to new projects and new lines, the activity code in ESP must be specified in:
Activity Code Custom Field Text The custom text field in the ESP in which the activity
code is specified. Example, if the value in this field is 2, the Activity Code/ Budget
Line Object Code must be specified in the ESP custom Text 2 field. Note Default value is 2. This field is mandatory. This field is enabled only for the new imports/ exports, and exports that are regenerated. You can view this field only if the Selection field is set to Single Project. Activity Description Custom Field Text The number of the custom text field in ESP in which the
activity description must be specified. Example, if the
value in this field is 2, then the Activity Description/ Budget Line Object
Description must be specified in the ESP custom Text 2 field. Note Default value is 3. This field is mandatory. This field is enabled only for the new imports/ exports, and exports that are regenerated. You can view this field only if the Selection field is set to Single Project. Activity Primary Key Custom Field Text The custom text field in the ESP in which the primary key
related to the activity is specified. Example, if the
value in this field is 2, the Activity Primary Key/ Budget Line Object Primary
Key must be specified in the ESP custom Text 2 field. Note Default value is 1. This field is mandatory. This field is enabled only for the new imports/ exports, and exports that are regenerated. You can view this field only if the Selection field is set to Single Project. OBS The code of the organization breakdown structure defined for the
activity that is linked to the project. Note You can view this field only if the Selection field is set to Single Project. Export OBS If this check box is selected, the organization breakdown structure data of the project is
exported to the external scheduling package. Note By default, this check box is cleared. Infor LN selects this check box if the Export OBS check box is selected in the Project Planning Parameters (tppss0100s000) session. You can view this field only if the Selection field is set to Single Project. OBS Outline Code The outline code of the external scheduling package that
must be mapped with the organization breakdown structure code in Infor LN. Note You can view this field only if the Selection field is set to Single Project.
Process Processes the XML file. Reset Selection Resets the Selection field to Single Project. This button is enabled only if the Multiple Import/Export check box is selected in the Project Selection (tppss2140m000) session. Disconnect Disconnects the link with the external scheduling
interface. This button is enabled when you have to:
| |||