This indicates the action you want to perform. You can save a
baseline by either creating a baseline or updating an existing baseline. A
baseline can be updated only if the baseline status is Free.
Create/Update Baseline (tppss2220m000)Use this session to create or update a baseline (planning) for a project. You can derive a new baseline from an existing (previous) baseline with status Free. If you create a baseline, you are in fact creating both a milestone baseline and an activity baseline.
Process Options This indicates the action you want to perform. You can save a
baseline by either creating a baseline or updating an existing baseline. A
baseline can be updated only if the baseline status is Free. Project The code that uniquely identifies the project for which you want
to save a baseline. Baseline The code that uniquely identifies the baseline (planning)
that you want to create or update. Derive from Previous Baseline If this check box is selected, the baseline (planning)
has to be derived from an existing baseline. If you choose to create a new
baseline with this option, you use the activity structure of an
existing (previous) baseline. Previous Baseline The code that uniquely identifies the existing baseline from