Performance Measurement Activity (tpppc5540m000)

Use this session to display performance measurement data.

 

Project
The code that identifies the project for which performance measurement data is displayed.
Description
The description or name of the code.
Generate Code
The generate codes store the performance measurement data.
Currency
The currency that is displayed is one of the home currencies. In performance measurement the currency array can be four deep. If you use an independent currency system you can rotate between four currencies. In a dependent situation you can also rotate between the home currencies, but the the amount times the displayed rate is not displayed in the calculated amount and is calculated using the reference currency.

Related topics

Description
The description or name of the code.
Activity
The code that identifies the activity.
Description
The description or name of the code.
Cost Period
The year of the cost control period. This is a display field.
Cost Period
The sequence number of the period linked to the amounts.
Cum.Incl.Commitments
Planned Value
The cumulative planned value including the hard commitment data.
Earned Value
The cumulative earned value including the hard commitment data.
Actual Cost
The cumulative actual costs including the hard commitment data.
Cost Variance
The cumulative cost variance including the hard commitment data. The formula used:
Cost Variance = earned Value - Actual Cost
CPI
The cumulative cost performance index including the hard commitment data.
Schedule Variance
The cumulative schedule variance. The formula used:
Schedule Variance = Earned Value - Planned Value
SPI
Cum.Excl.Commitments
Actual Cost
The cumulative actual costs excluding the commitment data.
Cost Variance
The cumulative cost variance excluding the commitment data .
Period Incl.Commit.
Earned Value
The earned value for the specified period, including the hard commitment data.
Actual Cost
The actual costs for the specified period, including the hard commitment data.
Cost Variance
The cost variance for the specified period, including the hard commitment data.
Schedule Variance
The schedule variance for the specified period.
Period Excl.Commit.
Cost Variance
The cost variance for the specified period, excluding the commitment data.
At Completion
BAC
The budget at completion for the project.
EAC
The estimate at completion for the project.
Variance at Completion
The cost variance at completion of the project. The variance is calculated using the formula:
Variance at Completion = BAC - EAC