Print Project Manager's Control Report (tpppc4413m000)

Use this session to print control reports at the element level. Reports can be based on element by cost type, cost component, control code, or cost object.

You can make a choice between two reports, while you are entering the print job:

  • The Foreman's Control Report, which prints budgeted/actual/allowed quantities.
  • The Project Manager's Control Report, which prints budgeted/actual/allowed amounts in the currency that is specified in this session.

 

Level to be Printed
The level on which the data is printed.

The levels at which cost control is generated are selected in the Project - Cost Control Levels (tppdm6102m000) session.

Sort By in Session tpppc4802m000

Payment Price per Unit
You can print out the amount per unit calculated from the budget line or calculated from the element. The formula is: amount per unit = amount / quantity
Calculation for Elementsthat cannot be Settled
Elements that cannot be settled can be included in the report with their actual progress or their allowed progress.
Period to
The year up to which the level is to be printed.
/
The period up to which the level is to be printed. The costs for the report are accumulated up to this period.
Currency
A generally accepted medium of exchange such as coins, treasury notes, and banknotes.

The following currency types are available in LN:

  • Home currency, which is used internally by companies to calculate costs, record budgets, and register tax amounts
  • Transaction currency, which is used in transactions with business partners, such as orders and invoices
Commitments
If this check box is selected, the commitments are taken as costs.
Sort Project by
Indicates how you want the project to be sorted.
Material
If this check box is selected, this cost control cost type is printed.
Labor
If this check box is selected, this cost control cost type is printed.