Standard Element (tppdm0180s000)Use this session to maintain details of the currently selected standard element. You can maintain a library of standard elements that you can copy from when you are maintaining a project.
General Element The element name. Description The description or name of the code. Search Key The search key of the current standard element. Sort Argument Use this field to register a characteristic of the element that you can use to sort elements in the following report sessions: Text If this check box is selected, a text is present. Control Standard Control Element The element defined as the control element. Costs are posted
to this element. Physical Progress If this check box is selected, project progress is
recorded for the current element. You can then use the Physical Progress Level field to specify the level
that you want to record progress at. If this check box is cleared, progress is recorded only at lower levels in the element budget
structure. Physical Progress Level Indicates the default level where project progress is
recorded. This field is available only if the Physical Progress check box is selected. Allowed values Cost Control If this check box is selected, cost control is
maintained for the standard element. If this check box is cleared, no
costs can be posted to the element. Invoicing Details Progress based Invoicing Indicates how the current element is to be
invoiced. Allowed values Progress for Invoice Indicates the type of work that makes up the
element. Allowed values Note This value is based on the value of the Progress based Invoicing field. If the Progress based Invoicing is set to:
To be Settled If this check box is selected, additional work relating to this element can
be settled. This applies only where the invoicing method is Progress Invoice and the work is Direct. Note This check box is enabled only if the Progress based Invoicing field is set to Yes. Billable If this check box is selected, the selected element can be invoiced to the
customer. Budget Details Quantity The quantity of the element (where applicable). Quantity The unit of measurement associated with the standard element. Time Unit The time unit appropriate to the element. Production Rate The number of units produced per time unit. This is relevant
if use is made of labor norms.
| |||