To structure the estimate

To create an estimate, the structural element with a top-down leading estimate type is required. In the Structural Elements (tpest1120m000) session, you can define the estimate type as top down or bottom up. The leading estimate type of a structural element determines the method of calculation of the estimate and you can also modify the estimate type.

Enter your top-down estimate in the Estimate Lines (tpest2100m000) session such as the line number, activity, description, estimate type, line level type, and amount in EURO.

Line 5TOPYachtTop downTotal60 million
Line 1001RedesigningTop downTotal9 million
Line 2002Building shipTop downTotal50 million
Line 2503DecoratingTop downTotal1 million

 

Element 03, Line 25, is subcontracted to another company. A request for a quotation is sent to the subcontractor, but the estimate for the cost is EURO 1 million.

Estimate lines

You must specify detailed estimate lines and you must define the entire estimate structure. Child activities, for which more bottom-up information is available, use the Bottom-Up leading estimate type option:

Structural ElementLETLaunch Level TypeCost Level TypeSales Level Type
TOP = The yachttop downdetailtotaltotal
01 = Redesigningtop downdetailtotaltotal
02 = Buildingtop downdetailtotaltotal
03 = Decoratingtop downdetailtotaltotal
011= CAD reworktop downdetailtotaltotal
021= Steelbottom updetaildetailtotal
022= Yard workbottom updetaildetailtotal
023= Enginebottom updetaildetailtotal

 

The structural element 011 is linked to 01. The structural element 021, 022, and 023 are linked to 02. Based on the linking, the 02 Building ship parent activity remains a top-down activity because of expected overhead costs.

Line numberActivityEstimate TypeLine Level TypeAmount in EURO
30021top downtotal30 million
35022top downtotal15 million
40023top downtotal2 million
45011top downtotal5 million
50011top downdetail3 million
55011top downdetail2 million
6002top downcost type (labor)4 million
6502top downcost type (material)46 million

 

Estimate details

In the example, a top-down estimate is used and amounts are allocated. However, the two internal departments involved in this project provide their own estimates for building the yacht. Based on their evaluation, they provide a more detailed calculation. Specify these lines and the related details in the estimate version.

Line numberActivityEstimate TypeLine Level TypeAmount in EURO
70011bottom uptotal5 million
80011bottom updetail2.7 million for engineering
81011bottom updetail0.3 million for project management
85023bottom updetail1 million
90022bottom updetail15 million
95021bottom uptotal40 million
10003bottom updetail0.5 million

 

If you view the details of the activity 011, a top-down total of EURO 5 million is expected. However, if you add the two bottom-up detail lines of 011, that part of the ship adds up to EURO 3 million or 5 million, depending on the Line Level Type. If all required estimate lines are specified, you can aggregate the totals and view the estimate amounts for the leading estimate type. For the formulas, refer to Estimate Lines (tpest2100m000) session.