Budgeted amountsUse the Budgeted Cost Component Costs (tpptc3541m000) session to view the budgeted project amount and the surcharge amount categorized by cost component, and by cost type within a cost component. In the case of each session below, you must specify both the required project and the budget cost analysis version. Budgeted project amounts: Use the following sessions to report on budgeted project costs by control code:
Use the following sessions to report on budgeted project costs by cost object:
To output budgeted amounts for the project, with a range of sort options, use the Print Budgeted Project Costs (tpptc3440m000) session. Budgeted element amounts: Use the following sessions to report on budgeted project costs by element:
To output budgeted amounts for the elements of the project, with a range of sort options, use the Print Budgeted Element Costs (tpptc3405m000) session. To print the actual budget, sorted by element, use the Print Budget by Element (tpptc3441m000) session. Budgeted activity amounts: Use the following sessions to report on budgeted project costs by activity:
To output budgeted amounts for the activities of the project, with a range of sort options, use the Print Budgeted Activity Costs (tpptc3415m000) session. To print the actual budget, sorted by activity, use the Print Budget by Activity (tpptc3443m000) session. Budgeted extension amounts: Use the following sessions to report on budgeted extension amounts:
Use the following sessions to report on extension amounts by control code within cost type:
Use the following sessions to report on extension amounts by cost object within cost type:
To output budgeted extension amounts, with a range of sort options, use the Print Budgeted Extension Costs (tpptc3425m000) sessions. To print the actual budget, sorted by extension, use the Print Budget by Extension (tpptc3426m000) session.
| |||