To use a plan

The Project Planning Parameters (tppss0100s000) session enables you to set parameters that relate to the Requirements Planning module. The planning parameters cover the default project plan and details that relate to the external scheduling package.

Setup a plan Requirements Planning includes a number of sessions that you can use to set up and maintain project plans:

  • Use the Plans (tppss0110m000) session to set up new plans or to change existing plans.
  • Use the Copy Plans (tppss0211m000) session to copy details from existing plans.
  • Use the Delete Plans (tppss0210m000) session to delete a plan or a range of plans.
  • Use the Print Plans (tppss0410m000) session to print plans in either summary or detailed format.

The information stored in each plan includes details of the top activity the plan uses, the name of the planner who initiated the plan, and the planned start and finish dates.

The active plan is visible in the Projects (tppdm6100m000) session. There can be only one active plan in a project. The active plan is :

  • The plan from which the baselines are created.
  • The plan for which progress can be entered.
  • The plan with which requirements are ordered.
  • The plan for which a budget can be frozen (control budget).