Generate Work Center Input/Output Control (tisfc3210m000)

Use this session to generate the input/output data for a range of work centers.

 

Work Center
The first of a range of work centers for which you want to calculate the input/output values.
Work Center
The last of a range of work centers for which you want to calculate the input/output values.
Include Partial Completions (Default)
If this check box is selected, LN also takes into account the routing operations that are only partially reported completed to calculate the input/output values.

If this check box is cleared, LN only takes into account the routing operations that are entirely reported completed to calculate the input/output values.

You can set the default value for the Include Partial Completions (Default) check box in the Production Order Parameters (tisfc0100s000) session.