Subcontracted Operations by End Item (tisfc2102m000)

Use this session to display subcontracted operations by end item.

You can either plan to subcontract operations when you define the operations' routing, or you can decide to subcontract an operation later, in the Subcontract Operations (tisfc2210m000) session.

 

Production Order
The order number of the subcontracted operation.
Production Order Status
The order status of the production order.

Allowed values

Order Status

End Item
An item that is ready to be delivered to a warehouse. An end item is produced at the end of a dangle routing (co-products and by-products) or a main routing.
General
Purchase Document
The number of the subcontracting purchase document.

LN treats subcontracting as buying a service. You can generate subcontracting purchase orders or subcontracting purchase requisitions in the Generate Subcontracting Purchase Documents (tisfc2250m000) session.

Slash Character
The position number of the subcontracting purchase order.
Subcontractor
A business partner that is hired to perform certain services, such as the execution of a part of a project or production order. The services are delivered via a purchase order.
Item
The main item of the production order.
Operated Item
The main item, or the phantom on which the operation is executed.

If the Operated Item field does not contain the same item as the Item field, the operated item is a phantom. In this case, the routing of the phantom is connected to the routing of the main item.

If the operated item is not a phantom, the main item and the operated item are the same.

Project (PCS)
The project that the production order is part of.
Operation
The sequence number of the operation to be carried out by the subcontractor.
Operation Status
The status assigned to an operation. For example, Planned, Ready to Start, or Completed. This status indicates how far an operation has proceeded.

Allowed values

Possible values

Next Operation
The operation that follows the current operation in the routing structure.

Related topics

Task
The task of the subcontracted operation.
Work Center
The subcontracting work center where the operation is performed.
Machine
The machine on which the operation is performed.
Operation Text
If this check box is selected, a text is present for the production order operation, which is linked in the production planning.
Task Text
If this check box is selected, a text is present for the task, which is linked in the Tasks (tirou0103m000) session.
Subcontracting Document
The type of document that is linked to the subcontracting operation.
Dates/Times
Remainder Start Date
The date you plan to start the operation, or if the operation has already been started, the date you plan to resume the operation.

You can choose whether LN uses the remaining order quantity or the hours already posted to calculate how much work has been carried out using the Calculation Method Remaining Production Time field in the Production Order Parameters (tisfc0100s000) session.

Move Start Date
The earliest date an operation can finish.

The move start date is calculated by subtracting the slack time from the number of days of the remaining production time after the start date remainder.

Quantities
Quantity Planned Input
The quantity you plan to start the operation with, including the quantity reported completed and rejects.

If you alter the scrap or yield values, LN will recalculate this field, to keep the quantity planned output the same.

Unit
The unit of measure in which the inventory of an item is recorded, such as piece, kilogram, box of 12, or meter.

The inventory unit is also used as the base unit in measure conversions, especially for conversions that concern the order unit and the price unit on a purchase order or a sales order. These conversions always use the inventory unit as the base unit. An inventory unit therefore applies to all item types, also to item types that cannot be kept in stock.

Quantity Planned Output
The quantity you plan to complete the operation with, which includes the quantity reported completed and the rejects.
Qty Returned from Subcontracting
The quantity that you have reported received from the subcontractor in the Purchase Order Lines (tdpur4101m000) session.
Subcontracting with Material Flow
Subcontracting with Material Flow
If this check box is selected, subcontracting with material flow is supported for the end items of this production order.
Note

During creation of the production order, the value of this check box is defaulted from the Subcontracting with Material Flow check box in the Items - Production (tiipd0101m000) session. After order creation, you can no longer change the setting of this check box on the production order.

Subassembly
An intermediary product in a production process that is not stored or sold as an end product, but that is passed on to the next operation.

For subcontracting purposes, a manufacturer can send a subassembly to a subcontractor to carry out work on the subassembly. This subassembly has its own item code defined in the Item Base Data.

After work is finished, the subcontractor sends the subassembly back to the manufacturer. Also this reworked subassembly has its own item code defined in the Item Base Data.

Subassembly Warehouse
The warehouse from which the subassembly is sent or in which the subassembly is received.
Overview
Work Center Type
The type of work center.

Allowed values

Work Center Type

Setup+Run Start Date
The date and time on which LN plans to start the operation.

If you alter the date and/or time of the Remainder Start Date field in the Production Planning (tisfc0110m000) session, LN recalculates the value of the Setup+Run Start Date field.

The start date of the operation is copied from planned production orders, which are generated in Enterprise Planning, when the orders are transferred from Enterprise Planning to Job Shop Control.

If the production order is transferred from the Production Order Advice (whina3100m000) session in Warehousing, LN copies the start date of the operation from that session.

When you manually enter an order in the Production Order (tisfc0101s000) session, LN calculates the value of the Setup+Run Start Date field using the lead-time elements of the operation that you specified in the Routing Operations (tirou1102m000) session.

Text
If this check box is selected, an operation text or a task text is present.
  • An operation text is linked in the production planning.
  • A task text is linked in the Tasks (tirou0103m000) session.
Ready
If this check box is selected, the purchase order was completed. You can close the order.

 

Apply
Only displays the subcontracted operations for the end item as entered in the End Item field.