Report Operations Complete by Order Group (tisfc0205m000)Use this session to report complete all the current operations for the production orders in an JSC order group.
Production Order Group The production order group for which you want to report all
current operations complete. EP Group Link The enterprise planning order group - if the current group has
been created in the Enterprise Planning package. Group Creator Logon The employee who created the JSC order group. Total Grouped Orders The total number of production orders in the JSC order group. Group Creation Date The date that the JSC order group was created. Show Count Points You can select (or clear) this check box by clicking Toggle 'show count points' on the appropriate menu. If this check box is selected, the first operation that is not completed and has a count point is displayed. If there are no operations with count points, the current operation is shown. You can define if an operation is count point in the Routing Operations (tirou1102m000) details session. If this check box is cleared, the current operation is displayed. Note When you select Report Complete from the appropriate menu, LN asks you if you want to continue to the next count point. If you answer Yes, all the operations until the next operation that is a count point are reported complete, for all the production orders in the order group. If no count point is found, all the operations in that production order are reported complete. Grouped Order Quantity The total order quantity for all the
production orders in the group. Note If the individual order quantities do not all have the same units of measurement, this field is meaningless. Production Order An order to produce a specified quantity of an item on a
specified delivery date. CurrentOperation The operation currently carried out with the earliest start
date. If more than one operation meets this criterion, the operation with the
lowest operation number is the current operation. There can be only one current
operation at any one time. S If this field reads S then the current operation is a start
operation (that is, there is no previous operation). E If this field contains an E then the current operation is an
end operation. Next Operation The operation that follows the current operation. Task The task of the
operation. Work Center The work center where the
operation is carried out. Operation Status The status assigned to an operation. For example, Planned, Ready to Start, or Completed. This status
indicates how far an operation has proceeded. Count Point If this check box is selected, the operation is a count point operation. You
can define an operation as a count point in the Routing Operations (tirou1102m000) details session. Quantity Planned Output The quantity planned output for
the operation. Quantity Completed The quantity of items reported as completed. Items that are
reported as completed can proceed with the upcoming operation. QuantityTo Inspect The quantity that has been sent to Quality for
inspection. This is the quantity from the most recent inspection order for this operation. Blocking Reason The reason an operation is temporarily not allowed to proceed. Reasons for blocking are:
Physical Location The name or description of where the orders are processed. You
can also use this field for any other information about the orders that is
common to the group. You can update this field for all members of the group
together with the Update Physical Location for Production Order Groups (tisfc0210m000) session. Note The physical location referred to in this field is not in any way related to a warehouse location. Initial Hidden Task The task that is performed in the operation. If anything is reported on the operation, you cannot change the task anymore. Work Center The work center where the task i s performed.
Report Complete Executes the process that you set up in this session. No Help topic is associated with this item. Toggle 'show count points' Click to select or clear the Show Count Points check box. Production Planning Click to start the Production Planning (tisfc0110m000) session. Blocked Operations by Production Order Click to start the Blocked Operations (tisfc0540m000) session. Backflush Materials and Hours Click to start the Backflush Materials and Hours (tisfc0220m000) session. Report Orders Completed Globally Click to start the Report Orders Completed Globally (tisfc0206m000) session.
| |||