Cost Component Scheme in ManufacturingA cost component scheme is a mandatory structure that specifies the breakdown the cost of an item to the level of detail you want using cost components. You can define this structure in the Cost Component Scheme (ticpr0109m000) session. Using user-defined cost components you can structure standard cost, sales prices and valuation prices breaking down the costs for every cost component in LN. In the Standard Cost Scheme Details (ticpr0110m000) session, you can collect all the cost components of the type Collect in a scheme. In other words, in the cost component structure, you can break down the cost to the level of detail you want: from completely aggregated to a detailed breakdown. Cost components are also used to:
Cost component codes are defined in the Cost Components (tcmcs0148m000) session, and assigned to one of the cost types:
Note The cost component type Not Applicable is used Project and Service. You must link a cost component of the applicable costing type to all entities in LN that are accountable for costs: materials, operations, surcharges, labor, and so on. Cost component structure set up
Cost Component scheme validation You must validate a new or modified cost component scheme before use. The validation process for individual schemes is initiated from the Cost Component Scheme (ticpr0109m000) and Cost Component Scheme (ticpr0609m000) sessions, and the validation of multiple schemes simultaneously in the Validate Cost Component Schemes (ticpr0209m000) session. To be valid, the cost component scheme must contain:
A valid cost component scheme has the Validated check box selected, and the date of validation displayed in the Last Validation Date field. If you modify a cost component scheme, the Validated check box is cleared and the date displayed in the Modified field in the Cost Component Scheme (ticpr0109m000) and Cost Component Scheme (ticpr0609m000) sessions. If the cost components scheme is modified, but not validated, the modifications can be removed using the Undo Scheme Modifications option. Modifications are effective only once the cost component scheme is validated. Note You can only use validated cost component schemes in the Items - Costing (ticpr0107m000), and Assembly Line Costing Data (ticpr0115m000) sessions. Booking costs on cost components During production of a manufactured item, all costs are booked on the cost component to which the costs are linked. These cost components can differ from the cost components in the end item's cost component structure.
After production, if you report an order as complete and the items are received in the warehouse, the costs are booked on the cost components as defined in the end item's cost component structure. If the Moment of Completion Posting field in the Production Orders (tisfc0501m000) session is Quantity Completed, the costs are booked as soon as a quantity of the production order is reported completed. Example Explanation: If you defined a detailed cost component SURCH_C for component item C in the Standard Cost Scheme Details (ticpr0110m000) session, and you want to report the costs posted to the detailed cost component SURCH_C separately for end item A, you must also define cost component SURCH_C in the chart details for end item A. If you do not define a cost component SURCH_C for item A, cost component SURCH_C becomes part of item A's aggregated cost component SURCH_A. You must define the detailed cost components of an item's cost component structure in the Standard Cost Scheme Details (ticpr0110m000) session.
| |||