The code of the MBC to
which revisions are linked.
E-Item by MBC (tiedm3122m000)Use this session to define and modify which engineering items are linked to an MBC line. If the E-items were generated using the Generate E-Items by MBC (tiedm3201m000) session, this session also enables you to apply changes.
MBC Number The code of the MBC to
which revisions are linked. MBC Number The order status. All Actions Must Apply to Item If this check box is selected, the engineering items
selected in the Include/Exclude E-Items (tiedm3121m000) session, to which all MBC lines
are applicable, will be considered for change. If this check box is cleared, the E-items selected in the Include/Exclude E-Items (tiedm3121m000) session, to which at least one MBC line is applicable, will be considered for change. Note The field relates to E-items which are both directly and indirectly listed in the Include/Exclude E-Items (tiedm3121m000) session. Position Select the position for the MBC item. Engineering Item Enter the engineering item for
the MBC. Engineering Item The description or name of the code. Old Revision The revision that is used
as the basis to change an E-item ( Engineering Item field). New Revision The new revision assigned to the E-item in the Engineering Item field. See the E-Item by MBC (tiedm3122m000) for more details. Effective Date of New Revision Enter the effective date for the new revision. This is the date
on which the revision will take effect.
Engineering Item Revisions Click to start the Engineering Item Revision (tiedm1100m000) session.
| |||