Estimated Material Distribution (ticst0508m000)Use this session to to view the amounts that are used to create financial transactions related to subcontracting WIP when subassemblies are received in inventory at estimated cost. Note
Production Order An order to produce a specified quantity of an item on a
specified delivery date. Status The status of the production order. Allowed values Position The position number that identifies the estimated material in
the Estimated Materials (ticst0101m000) session. Item The item that is used as
material in production. Rework Order If this check box is selected, the production order is
a rework order. Estimated Costs Are Frozen If this check box is selected, the estimated end item
unit costs have been frozen, which means they can no longer be
modified. The moment the estimated end item unit costs are frozen depends on the Moment Freezing Estimates field. Estimated Quantity The estimated material quantity for the entire production
order. Estimated Quantity The unit of measure in which the inventory of an item is
recorded, such as piece, kilogram, box of 12, or meter. The inventory unit is also used as the base unit in measure conversions, especially for conversions that concern the order unit and the price unit on a purchase order or a sales order. These conversions always use the inventory unit as the base unit. An inventory unit therefore applies to all item types, also to item types that cannot be kept in stock. Backflushing If this check box is selected, the materials for the
production order are issued through backflushing. Default value The default for this field is the Backflush Materials field in the Estimated Materials (ticst0101m000) session. Serialized items Serialized items can only be backflushed if in the Items - Warehousing (whwmd4500m000) details session the Serials in Inventory check box is cleared, and the Register Serial Issue During As Built field is Yes. In all other cases, serialized items cannot be backflushed. If the serialized item is lot-controlled, the lot from which the items are backflushed is based on the outbound method ( Last In First Out (LIFO), First In First Out (FIFO)) as is defined in the Items - Warehousing (whwmd4500m000) details session. . Unit Series The effectivity series code. Distribution Type The distribution type for the materials to be
issued. Allowed values Distribution Line The distribution line number related to the peg. Project A collection of manufacturing and purchasing actions that are
performed especially for a particular customer order. A project is initiated to
plan and coordinate the production of these items. For a standard-to-order production, the project is only used to link the item with the customer order. Otherwise, a project can include:
Element Activity Project Peg Origin The origin of the project peg for the production
order. Allowed values Effectivity Unit A means to control the validity of variations by effectivity
units. Unit effectivity enables you to model changes for the following entities:
Unit Series A code that represents a group of one or more effectivity units
that applies to the same unit effective item. Unit Sequence The sequence number of the effectivity unit. Net Quantity Scrap Quantity The scrap quantity of the material. Estimated Quantity The estimated material quantity. Note The sum of all the estimated material quantities by effectivity unit must equal the estimated material quantity for the entire production order. Split-Off Distribution Line If this check box is selected, the distribution line
was split off. This line is stored for reference purposes only. For example, in
case you want to send back project-pegged materials that were issued before
splitting the order. Note A split off distribution line can contain an actual quantity of material if it is issued before performing the order split. A split off distribution line is visible only when the Hide Split-Off Distribution Lines command is not marked.
Production Warehouse Orders Starts the Production Warehouse Orders (timfc0101m000) session. Next Level Requirements Starts the Next Level Requirements (cprrp0541m100) session. Top Demand Order References Starts the Top Demand Order References (cprrp0541m200) session. Hide Split-Off Distribution Lines If this command is marked, split off distribution lines are not
shown in this session.
| |||