Select the cost component view you require.
Print Differences between Frozen and Current Estimated Costs (ticst0411m000)Use this session to print the differences between the frozen and the current end item unit costs by Cost Component Scheme in Manufacturing, and by work center. The current end item unit costs are calculated for the current date.
Cost Component Select the cost component view you require. Cost View Select the cost view you require. Allowed values Suppress Equal Values If this check box is selected, and if the frozen
estimated costs and the current estimated costs are equal for a cost component, LN does not print a line
on the report. Check Existence of Material Standard Costs During calculation, LN reads the material standard costs to get the
sum of material costs of the operation or production order. If a standard cost
is not (yet) calculated, the material costs can be lower then the real
estimated value. If this check box is selected, LN checks if all standard cost of materials are calculated. If a standard cost is not present, LN generates an error report and terminates the calculation. If this check box is cleared, no additional check is done on the standard cost of materials. This means that the estimated value of material costs can be lower, and production results are possible. Print Only Production Orders with Frozen Estimates If this check box is selected, LN prints only production orders with frozen
estimates.
| |||