Assembly Order - WIP Estimates (tiasc7500m000)Use this session to display WIP estimates for assembly orders. WIP estimates are the estimated costs per order, per line. The estimated WIP is based on the order content as it is on the moment the order is frozen. The costs can be split up in cost components.
Assembly Order Assembly Line A set of consecutive line stations in which FAS (Final Assembly
Schedule) items are manufactured. The items are manufactured by passing the
items from line station to line station and by carrying out operations at each
line station. An assembly line is subdivided into a number of line segments
separated by buffers. An assembly line can be either a main line or a supplying
line. Calculation Date When the WIP estimates were calculated. Cost Component A cost component is a user-defined category for the
classification of costs. Cost components have the following functions:
Cost components can be of the following cost types:
Note If you use Assembly Control (ASC), you cannot use cost components of the General Costs type. Amount The size of the cost component.
| |||