Purchase Contract Line Detail Analysis (tdpur3513m100)Use this session to have a results analysis for a purchase contract line detail based on its cumulated quantities and amounts, which are also shown in this session. Note The availability of various fields depends on the setting of the Log Turnover on Contract check box in the Purchase Contract Parameters (tdpur0100m300) session.
Contract The number of the purchase contract. Contract Line Status The status of the of the parent purchase contract line, and
therefore, of the purchase contract line detail. Allowed values Line The number of the purchase contract line. Purchase Office A department in your organization that is responsible for
buying the materials and services required by your organization. You assign
number groups to the purchase office. Sequence The number of the purchase contract line detail. Buy-from Business Partner The business partner from whom you order goods or services;
this usually represents a supplier's sales department. The definition includes
the default price and discount agreements, purchase-order defaults, delivery
terms, and the related ship-from and invoice-from business partner. Item The raw materials, subassemblies, finished products, and tools
that can be purchased, stored, manufactured, and sold. An item can also represent a set of items handled as one kit, or which exist in multiple product variants. You can also define nonphysical items, which are not retained in inventory but can be used to post costs or to invoice services to customers. The examples of nonphysical items:
Price Group A group of items to which the same pricing characteristics
apply. Effectivity Unit A means to control the validity of variations by effectivity
units. Unit effectivity enables you to model changes for the following entities:
Current Date The current date and time, which is filled automatically when
you start this session. Effective Date The first day on which a record or a setting is valid. The
effective date often includes the effective time. Expiry Date The expiry date of the contract. Time Elapsed The time elapsed is expressed as a percentage of the total
contract duration, as specified in the Purchase Contracts (tdpur3100m000) session. The calculation for the time elapsed: (Current Date - Effective Date ÷ ((Expiry Date - Effective Date) + 1)) * 100% Agreed Quantity The purchase contract line detail's contract quantity. Purchase Unit The unit in which you purchase an item, also referred to as
the purchase quantity unit. Agreed Quantity The purchase contract line detail's contract quantity. Inventory Unit The unit of measure in which the inventory of an item is
recorded, such as piece, kilogram, box of 12, or meter. The inventory unit is also used as the base unit in measure conversions, especially for conversions that concern the order unit and the price unit on a purchase order or a sales order. These conversions always use the inventory unit as the base unit. An inventory unit therefore applies to all item types, also to item types that cannot be kept in stock. Minimum Quantity The purchase contract line detail's minimum contract quantity. Minimum Quantity Maximum Quantity The purchase contract line detail's maximum contract quantity. Note If the maximum quantity is reached, the Action on Exceeding Maximum Quantity field determines the action that must be executed. Maximum Quantity Advised Quantity The advised quantity for the purchase contract line detail,
which includes the scheduled quantities of all the purchase schedule lines with
the Created status that are linked to the contract line
detail. Advised Quantity The advised quantity for the purchase contract line detail,
which includes the scheduled quantities of all the purchase schedule lines with
the Created status that are linked to the contract line
detail. Called Quantity The sum of the called quantities of all the purchase schedule lines that are linked to the
contract line detail. The called quantity is increased when a schedule line is linked to a contract. The called quantity is decreased again when a schedule line is processed in the Process Purchase Schedules (tdpur3223m000) session. Called Quantity The sum of the called quantities of all the purchase schedule lines that are linked to the
contract line detail. The called quantity is increased when a schedule line is linked to a contract. The called quantity is decreased again when a schedule line is processed in the Process Purchase Schedules (tdpur3223m000) session. Invoiced Quantity The sum of the invoiced quantities of all purchase schedule lines that are linked to the
contract line detail. The invoiced quantity is increased when linked purchase schedule lines are processed in the Process Purchase Schedules (tdpur3223m000) session. Invoiced Quantity The sum of the invoiced quantities of all purchase schedule lines that are linked to the
contract line detail. The invoiced quantity is increased when linked purchase schedule lines are processed in the Process Purchase Schedules (tdpur3223m000) session. Remaining Quantity The remaining quantity, expressed in the purchase unit. The calculation for the remaining quantity: Agreed quantity - Called quantity - Invoiced quantity. Remaining Quantity The remaining quantity, expressed in the inventory unit. The calculation for the remaining quantity: Agreed quantity - Called quantity - Invoiced quantity. Required CUM The required cumulative aggregated from all schedules that are linked to this
purchase contract line detail, expressed in the purchase unit. Required CUM The required cumulative aggregated from all schedules that are linked to this
purchase contract line detail, expressed in the inventory unit. Received CUM The received cumulative aggregated from all schedules that are linked to this
contract line, expressed in the purchase unit. Received CUM The received cumulative aggregated from all schedules that are linked to this
contract line, expressed in the inventory unit. Used Quantity Total Quantity Expected Quantity The calculated quantity that you expect to have purchased at
the end of the contract, expressed in the purchase unit. This calculation is
extrapolated from the contract's ordered quantity that is registered during the
part of the effective period that has passed. Expected Quantity The calculated quantity that you expect to have purchased at
the end of the contract, expressed in the inventory unit. This calculation is
extrapolated from the contract's ordered quantity that is registered during the
part of the effective period that has passed. Usage The total number of called items and invoiced items expressed as
a percentage of the agreed contract quantity. Remaining Usage The total number of remaining items (not called or invoiced) expressed as a
percentage of the aggregated agreed contract quantity. Expected Usage The percentage of the items that you should have purchased,
which is calculated using the agreed quantity and effective period. Called Amount The sum of the called amounts of all purchase schedule lines that are linked to the contract
line detail. The called amount is increased when a schedule line is linked to a contract. The called amount is decreased again when a schedule line is processed in the Process Purchase Schedules (tdpur3223m000) session. Invoiced Amount The sum of the invoiced amounts of
all purchase schedule lines that are linked to the contract line detail. The invoiced amount is increased when linked purchase schedule lines are processed in the Process Purchase Schedules (tdpur3223m000) session.
| |||