Request for Quotation (tdpur1600m000)Use this session to view, enter, maintain, and process a specific request for quotation (RFQ) and linked request for quotation (RFQ) lines. This session supports easy RFQ entry. You can perform all the actions on one screen. This session enables you to quickly enter the most important information for an RFQ and to process the RFQ.
Tabs The lines on the tabs refer to these sessions:
Note You cannot delete an RFQ line if a bidder is linked to the RFQ or if an alternative RFQ line is present for the current RFQ line.
RFQ The number of the request for quotation (RFQ). Reference A The first extra reference by which the order or request for
quotation can be identified. This reference is printed on various order
documents and lists. Reference B The second extra reference field that you can fill with extra
information. This reference is printed on the order documents and lists. Buyer The employee of your company who is the contact to the
concerned buy-from business partner. The buyer is also known as the purchasing
agent. Default value LN retrieves the default buyer from the Purchase User Profiles (tdpur0143m000) session. Status The status of the RFQ. Allowed values RFQ Date The date on which the request for quotation is specified. Default value The current (creation) date, or the requisition date if the RFQ was generated from a converted requisition. Note This date can be manually changed to a date in the past or in the future. Response Date The last date on which the bidder can submit an RFQ response on
the request for quotation. Default value The default response date is determined by the number of days defined in the Default Term for Returning RFQ's field of the Request for Quotation Parameters (tdpur0100m100) session. The number of days defined in this Default Term for Returning RFQ's field is added to the RFQ date. Example If the RFQ date is 2000-01-01, and the value of the Default Term for Returning RFQ's field is 10 days, LN comes up with the default response date 2000-01-11. Note If the response date has expired, and no RFQ response is submitted on the request for quotation (RFQ), you can remove the RFQ in the Delete Requests for Quotation (tdpur1205m000) session. The response date on the RFQ header is used as the default response date for all bidders who are selected for the RFQ. The default response date for the bidders can be overwritten in the RFQ Bidders (tdpur1505m000) session. The response date cannot be before the RFQ date. Receipt Date The date on which the items, for which you send the request for
quotation, are planned to be delivered. Note When you accept the RFQ response and you copy the RFQ in the Convert RFQs (tdpur1202m000) session, the receipt date is copied to the purchase order or purchase contract. The receipt date cannot be before the response date. Start Receipt Period The start date of the period that the items, for which you send
the request for quotation, are scheduled to be delivered. Note
End Receipt Period The end date of the period that the items, for which you send
the request for quotation, are scheduled to be delivered. Note
Purchase Office A department in your organization that is responsible for
buying the materials and services required by your organization. You assign
number groups to the purchase office. Warehouse The warehouse where the
items must be delivered. Note
Receipt Address The address of the warehouse or place where the goods must be
delivered. Delivery Terms The agreements with the business partner, concerning the way
the goods are delivered. Relevant information is printed on various order
documents. Note You can also specify delivery terms per bidder in the RFQ Bidders (tdpur1505m000) session. Point of Title Passage The point at which the legal ownership changes. At this point,
the risk passes from the seller to the buyer. Payment Terms Agreements about the way in which invoices are paid. The payment terms include:
The payment terms allow you to calculate:
Note You can also specify payment terms per bidder in the RFQ Bidders (tdpur1505m000) session. Apply Landed Costs If this check box is selected, landed costs can be linked to this RFQ. Default value The value of the Apply Landed Costs on Request for Quotation check box in the Landed Costs Parameters (tclct0100m000) session.
Generate Requests for Quotation Starts the Generate Requests for Quotation (tdpur1220m000) session. Convert RFQs Starts the Convert RFQs (tdpur1202m000) session. Process Non-Converted RFQ Responses Starts the Process Non-Converted RFQ Responses (tdpur1223m000) session. Delete Requests for Quotation Starts the Delete Requests for Quotation (tdpur1205m000) session. Order Pegging Starts the Browse Order Pegging (cprrp0740m000) session. Add Bidders to RFQ Starts the Add Bidders to RFQ (tdpur1221m000) session. RFQ - Lines - Synchronization Starts the RFQ - Lines Synchronization (tdpur0280m000) session. RFQ History Starts the RFQ History (tdpur1550m000) session.
| |||