Request for Quotation (tdpur1600m000)

Use this session to view, enter, maintain, and process a specific request for quotation (RFQ) and linked request for quotation (RFQ) lines.

This session supports easy RFQ entry. You can perform all the actions on one screen. This session enables you to quickly enter the most important information for an RFQ and to process the RFQ.

  • You can start this session from the Requests for Quotation Overview (tdpur1501m000) overview session, by double-clicking a record, or by entering a new RFQ. You can also start this session stand-alone.
  • To view the details of the RFQ header, click RFQ Details on the File menu of the current session. Consequently, the Requests for Quotation Overview (tdpur1501m000) details session starts.
Tabs

The lines on the tabs refer to these sessions:

  • RFQ Lines
    Refers to the Request for Quotation Lines (tdpur1502m000) session. On this tab, you can enter and view the lines of the RFQ. Double-click the line for more detailed information.
  • Bidders
    Refers to the RFQ Bidders (tdpur1505m000) session. On this tab, you can view and link the bidders to whom the RFQ must be sent.
  • Responses
    Refers to the RFQ Responses (tdpur1506m000) session.

    On this tab, you can:

    • View RFQ response data by bidder and RFQ line. You cannot change the data for response lines with the Created status in the RFQ Responses (tdpur1506m000) session.
    • View, enter, and maintain the RFQ response data. After an RFQ is printed for a bidder, and as a result, its status is Sent, you can specify response data in the RFQ Responses (tdpur1506m000) session.
Note

You cannot delete an RFQ line if a bidder is linked to the RFQ or if an alternative RFQ line is present for the current RFQ line.

 

RFQ
The number of the request for quotation (RFQ).
Reference A
The first extra reference by which the order or request for quotation can be identified. This reference is printed on various order documents and lists.
Reference B
The second extra reference field that you can fill with extra information. This reference is printed on the order documents and lists.
Buyer
The employee of your company who is the contact to the concerned buy-from business partner. The buyer is also known as the purchasing agent.

Default value

LN retrieves the default buyer from the Purchase User Profiles (tdpur0143m000) session.

Status
The status of the RFQ.

Allowed values

RFQ Status

RFQ Date
The date on which the request for quotation is specified.

Default value

The current (creation) date, or the requisition date if the RFQ was generated from a converted requisition.

Note

This date can be manually changed to a date in the past or in the future.

Response Date
The last date on which the bidder can submit an RFQ response on the request for quotation.

Default value

The default response date is determined by the number of days defined in the Default Term for Returning RFQ's field of the Request for Quotation Parameters (tdpur0100m100) session. The number of days defined in this Default Term for Returning RFQ's field is added to the RFQ date.

Example

If the RFQ date is 2000-01-01, and the value of the Default Term for Returning RFQ's field is 10 days, LN comes up with the default response date 2000-01-11.

Note

If the response date has expired, and no RFQ response is submitted on the request for quotation (RFQ), you can remove the RFQ in the Delete Requests for Quotation (tdpur1205m000) session.

The response date on the RFQ header is used as the default response date for all bidders who are selected for the RFQ. The default response date for the bidders can be overwritten in the RFQ Bidders (tdpur1505m000) session.

The response date cannot be before the RFQ date.

Receipt Date
The date on which the items, for which you send the request for quotation, are planned to be delivered.
Note

When you accept the RFQ response and you copy the RFQ in the Convert RFQs (tdpur1202m000) session, the receipt date is copied to the purchase order or purchase contract.

The receipt date cannot be before the response date.

Start Receipt Period
The start date of the period that the items, for which you send the request for quotation, are scheduled to be delivered.
Note
  • When you accept the RFQ response and you copy the RFQ in the Convert RFQs (tdpur1202m000) session, the start date is copied to the purchase order, or the purchase contract.
  • The start date of the receipt period cannot be before the response date.
  • You cannot define a receipt period if a receipt date is defined.
End Receipt Period
The end date of the period that the items, for which you send the request for quotation, are scheduled to be delivered.
Note
  • When you accept the RFQ response and you copy the RFQ in the Convert RFQs (tdpur1202m000) session, the end date is copied to the purchase order or the purchase contract.
  • The end date of the receipt period cannot be before the start date.
  • You cannot define a receipt period if a receipt date is defined.
Purchase Office
A department in your organization that is responsible for buying the materials and services required by your organization. You assign number groups to the purchase office.
Warehouse
The warehouse where the items must be delivered.
Note
  • If you specified a warehouse, the Receipt Address field must also be filled.
  • You cannot enter a warehouse of the type Shop Floor.
Receipt Address
The address of the warehouse or place where the goods must be delivered.
Delivery Terms
The agreements with the business partner, concerning the way the goods are delivered. Relevant information is printed on various order documents.
Note

You can also specify delivery terms per bidder in the RFQ Bidders (tdpur1505m000) session.

Related topics

Point of Title Passage
The point at which the legal ownership changes. At this point, the risk passes from the seller to the buyer.

Related topics

Payment Terms
Agreements about the way in which invoices are paid.

The payment terms include:

  • The period within which invoices must be paid.
  • The discount granted if an invoice is paid within a given period

The payment terms allow you to calculate:

  • The date on which the payment is due
  • The date on which the discount periods expire
  • The discount amount
Note

You can also specify payment terms per bidder in the RFQ Bidders (tdpur1505m000) session.

Apply Landed Costs
If this check box is selected, landed costs can be linked to this RFQ.

Default value

The value of the Apply Landed Costs on Request for Quotation check box in the Landed Costs Parameters (tclct0100m000) session.

 

Generate Requests for Quotation
Convert RFQs
Starts the Convert RFQs (tdpur1202m000) session.
Process Non-Converted RFQ Responses
Delete Requests for Quotation
Order Pegging
Add Bidders to RFQ
RFQ - Lines - Synchronization
RFQ History
Starts the RFQ History (tdpur1550m000) session.