The code that identifies the schedule segment.
Schedule Segments (tdipu0115m000)Use this session to list and maintain purchase schedule segments. A segment can be specified by adding a segment time unit, a segment length, and a requirement type. If you use nonreferenced schedules, segment sets are used to:
If you use referenced schedules, no segment sets are used because these schedules are immediately put into a purchase release with the status Scheduled. Consequently, the requirement type is always Firm.
Segment The code that identifies the schedule segment. Segment Time Unit The time unit in which the segment is expressed, for example
days, weeks, months, and so on. Allowed values Segment Length The period that is assigned to the segment. The period is
expressed in the segment time unit. Requirement Type Use this field to link a specific requirement type to each segment (code). Note For the Immediate requirement type, you cannot define a segment time unit and a segment length as this requirement type involves undelivered requirements from the past that must be shipped as soon as possible. Allowed values
| |||