The days you want to view, or specify unavailable.
Non-working Days (tcccp0119m000)Use this session to view and manage days that are not available for production and cannot be scheduled in a specific calendar. Note To define unavailable days that have a pattern, such as a national holiday that reoccurs every year, use the Calendar Exceptions (tcccp0144m000) session.
Calendar Code The days you want to view, or specify unavailable. Period Displays for which day, week, 4 weeks, month, quarter, half
year, or year LN displays the unavailable days. To change the period definition, click one of the following icons:
To change the period definition to the values mentioned above or to one of the following options, on the appropriate menu, click View By:
Default value Year Period Dates Displays the start and the end date of the period in which the
unavailable days are specified. Date Displays the date of an unavailable day. To define a new
unavailable day for the specified calendar, click Add a New Record. Description Specify why a specific day is not available for the calendar
code.
Go to Today Click to display the unavailable days for the period in which
the current day falls. View By Select to change the size of the period for which LN displays the
unavailable days. Day Sets the period to Day. Week Sets the period to Week. 4 Weeks Sets to set the period to 4 Weeks. Month Sets the period to Month. Quarter Sets the period to Quarter. Half Year Sets the period to Half Year. Year Sets the period to Year. Go to Date Specifies the date of the period for which LN must display the
unavailable days. Next Period Displays the next period. Previous Period Displays the previous period.
| |||