Non-working Days (tcccp0119m000)

Use this session to view and manage days that are not available for production and cannot be scheduled in a specific calendar.

Note

To define unavailable days that have a pattern, such as a national holiday that reoccurs every year, use the Calendar Exceptions (tcccp0144m000) session.

 

Calendar Code
The days you want to view, or specify unavailable.
Period
Displays for which day, week, 4 weeks, month, quarter, half year, or year LN displays the unavailable days.

To change the period definition, click one of the following icons:

  • Day
  • Week
  • Month
  • Year

To change the period definition to the values mentioned above or to one of the following options, on the appropriate menu, click View By:

  • 4 Weeks
  • Quarter
  • Half Year

Default value

Year

Period Dates
Displays the start and the end date of the period in which the unavailable days are specified.
Date
Displays the date of an unavailable day. To define a new unavailable day for the specified calendar, click Add a New Record.
Description
Specify why a specific day is not available for the calendar code.

 

Go to Today
Click to display the unavailable days for the period in which the current day falls.
View By
Select to change the size of the period for which LN displays the unavailable days.
Day
Sets the period to Day.
Week
Sets the period to Week.
4 Weeks
Sets to set the period to 4 Weeks.
Month
Sets the period to Month.
Quarter
Sets the period to Quarter.
Half Year
Sets the period to Half Year.
Year
Sets the period to Year.
Go to Date
Specifies the date of the period for which LN must display the unavailable days.
Next Period
Displays the next period.
Previous Period
Displays the previous period.