Next Level Requirements (cprrp0541m100)Use this session to view the next level demand orders for a project peg distribution line. One distribution line can match multiple demand orders, with different demand dates.
Required Date Date on which the item is required according to the demand
order. Required Quantity The quantity that is fulfilled for each demand order. This can
be less than the required quantity for the demand order. For example, a distribution line is present for project peg A with a quantity of 10 pieces. Due to lot sizing, this line is for 10 pieces, while two demand orders are present for 8 pieces each (thus totalling 16) for project peg A. In this situation, the next level requirements display two lines:
Multiple Top Demand References If there are more than one independent demand order for this
next level requirement Yes is
displayed. No Top Demand Present If there is no top demand present for this next level
requirement, Yes is displayed. Initial Hidden Order Type View the order type of the demand order: Allowed values
Planned Order A supply order in Enterprise Planning that is created for planning
purposes, but which is not an actual order yet. Enterprise Planning works with planned orders of the following types: Planned orders are generated in the context of a particular scenario. The planned orders of the actual scenario can be transferred to the execution level, where they become actual supply orders. Position Number Plan Item An item with the order system Planned. The production, distribution, or purchase of these items is planned in Enterprise Planning based on the forecast or the actual demand. You can plan these items by means of the following:
Plan items can be one of the following:
A group of similar plan items or families is called a product family. The items are aggregated to give a more general plan than the one devised for individual items. A code displayed by the item code's cluster segment shows that the plan item is a clustered item that is used for distribution planning.
Top Demand Order References Start the Top Demand Order References (cprrp0541m200) session.
| |||