Plan Items - Optimized Lot Sizes (cprao3110m000)

Use this session to view the optimized lot sizes and order intervals that LN calculated in the Optimize Lot Sizing (cprao3200m000) session.

 

Scenario
The scenario for which LN displays the optimized lot sizes and order intervals.
Plan Item
The plan item for which LN displays the optimized lot sizes and order intervals.
Order Interval
The optimized order interval for the specified plan item.

The order interval is expressed in calendar days.

Use the Copy Lot Sizes to Item Ordering Data option from the appropriate menu to copy the optimized order interval to the Order Interval field in the Items - Ordering (tcibd2100m000) session.

Lot Size
The optimized lot size for the specified item

Select the Copy Lot Sizes to Item Ordering Data option from the appropriate menu to copy the lot size to the Economic Order Quantity field in the Items - Ordering (tcibd2100m000) session.

Old Lot Size
The lot size before optimization.
Resource
The resource for which the item parameters are optimized.

If the routing of an item contains multiple resources, this field displays the resource with the highest priority.

Computed Cost
The cost associated with this parameter setting.
Note

This is the cost over the total time period for which the logistic parameters have been optimized.

Cost Advantage
The difference between the cost of the optimized lot size and the cost of the currently effective lot size.

The currently effective lot size is defined in the Items - Ordering (tcibd2100m000) session.

This field indicates the cost advantage that can be realized if you copy the optimized parameters to the Item Base Data module.

Note

The cost is calculated for the total time period over which the logistic parameters were optimized.

Copy
If this check box is selected, you can copy the optimized values to the actual order parameters, if you select Copy Lot Sizes to Item Ordering Data from the appropriate menu.