Possible Values

  • Priority

    LN first uses the suppliers or supplying relationships with the highest priority. You can define the priority in the Item - Purchase Business Partner (tdipu0110m000) session and in the Supplying Relationships (cprpd7130m000) session.

  • Least Cost

    LN first uses the suppliers or supplying relationships with the lowest cost. This cost includes material cost, production cost, and supply cost.

    This option is only available if the supply type is Distribution.

  • Min. Transport Time

    LN first uses the suppliers with the shortest supply time. LN first uses the supplying relationships with the shortest supply lead time.

    You can define the supply time in the Item - Purchase Business Partner (tdipu0110m000) session and you can define the supply lead time in the Supplying Relationships (cprpd7130m000) session.

  • Min. Transport WIP

    LN first uses the suppliers with the lowest transportation WIP. The transportation WIP (work in process) is the supply time multiplied by the item cost.

    This option is only available if the supply type is Distribution.