Project Hours (bptmm1111m000)

Use this session to register hours spent on a project activity.

The hours input comes from:

  • Assignments
    From the appropriate menu, select Use Assignments. See also the Assignments (bpmdm0130m000) session.
  • Manual entry
    Click the New button on the toolbar or, from the File menu, select New.
  • Global registration of hours
  • Distributing team hours
Note
  • You can either enter hours per day (only if the period duration is less than or equal to seven days), or enter a total of hours per task.
  • If you enter a total amount, you can enter one text block per line. If you enter hours per day, each day has its own text block.
  • On the View menu, click Customize Grid to display description fields for the following:

    • Project
    • Element
    • Activity
    • Extension

 

Task
An activity to manufacture or repair an item. For example, sawing, drilling, or painting.

A task is carried out on a work center, and can be related to a machine.

Cost Component
A cost component is a collection of cost objects with a certain characteristic. A cost component does not depend on the cost type, therefore, for example, a project can be monitored from another dimension. For example, all the costs that refer to electrical work, for example, cable and installation work, are visible if the applicable cost objects are linked to the cost component Electrical work.
Billable
If this check box is selected, the hours can be invoiced.
Labor Type
The classification of work performed, and the time of day at which the work is performed (either normal working hours or overtime). Based on the kind of work and the hour type, you can use labor types to specify surcharges so that LN can calculate the actual labor costs in People.
Overtime
If this check box is selected, the entered labor hours are seen as overtime.

You cannot manually change this setting: it is determined by the labor type used on the time line.

Hours Distribution Done
If this check box is selected, the hours were distributed among the team members.
Sequence Number
The number that identifies a data record or a step in a sequence of activities. Sequence numbers are used in many contexts. Usually LN generates the sequence number for the next item or step. Depending on the context, you can overwrite this number.
Employee
The employee's code.
Employee
The employee's name.
Team
The code of the team to which the employee belongs.
Team
The name of the team.
Year/Period
The year for which you register hours.

The year and the period code identify a unique period.

Period
The identification of a period table. The different periods of a year, including the period number, start date and end date are linked to the period-table code.
Start Date
The project start date.
End Date
The project end date.
Project
An endeavor with a specific objective to be met within the prescribed time and financial limitation, and that has been assigned for definition or execution.
Element
The smallest part of an element structure. An element is used to define the (structure of the) work of the project, so that you can carry it out.
Activity
The smallest part of the activity structure used for a time-scaled budget. An entity that is used to represent a part of a project in an activity structure.

LN distinguishes these activity types:

  • WBS Element
  • Control Account
  • Work Package
  • Planning Package
  • Milestone
Extension
The specific agreements within or in addition to the initial contract. An extension falls outside the initial contract with the sold-to business partner. Extensions can be assigned to the bottom-up budget.

LN distinguishes four extension types:

  • Scope Change
  • Provisional Amount
  • Fluctuation Settlement
  • Quantities to be Settled
Current View
The unit in which the hours of the current view are expressed.
Current View
The number of regular hours in the current view.
Current View
The number of overtime hours in the current view.
Total
The unit in which the totals are expressed.
Total
The total number of regular hours.
Total
The total number of overtime hours.
Employment
The unit in which employment is expressed.
Employment
The number of regular hours that an employee works per defined period.
Line Origin
Indicates how the hours line was created.

This field can have one of the following values:

  • Manual
  • Assignment
  • Global Registration
  • Team Hours
  • Backflushing
  • Day-End Hours
  • External
Logon Code
The identification code for the LN user. This code is used for system security.
Transaction Date
The date and time the hours line was created.
Approved
If this check box is selected, the hours of this line were approved.
Processed
If this check box is selected, the hours of this line were processed to Financials.
Text
If this check box is selected, a text is present.
Path for Labor Cost Rate
The labor rate for hours registration search path set in the Projects (tppdm6100m000) session.
Labor CostRate Code
The cost rate retrieved from the Labor Rate Code - Rates (tcppl0191m000) session or the Specific Labor Rates (tcppl0192m000) session.
Trade Group
The trade group retrieved from the Employees - Project (tppdm8101m000) session.
Currency
The currency in which the cost rate is expressed.
Estimated Labor Costs
The estimated cost amount.
Path for Labor Sales Rate
The labor rate for hours registration search path set in the Projects (tppdm6100m000) session.
Labor SalesRate Code
The sales rate retrieved from the Labor Rate Code - Rates (tcppl0191m000) session or the Specific Labor Rates (tcppl0192m000) session.
Currency
The currency in which the sales rate is expressed.
Estimated Labor Sales
The estimated sales amount.
Text For The Period
Room for comments for the entire period or for the first day of the applicable period.
Text
Room for comments.

 

Get Assignments
Starts the Assignments (bpmdm0130m000) session.
Create Assignments
Creates an assignment for the selected lines.
Close Assignments
Closes the assignment associated with the selected lines.
Delete Assignments
Removes the assignment associated with the selected lines. As a result, the assignment will no longer be shown in the Assignments (bpmdm0130m000) session.
Copy Hours and Expenses
Starts the Copy Hours and Expenses (bptmm1210m000) session.
Global Registration of Hours
Starts the Global Registration of Hours (bptmm1201m000) session.
Distribute Team Hours
Starts the Distribute Team Hours (bptmm1220m000) session.
Process Now
Use this command to process hours without closing the session.
Approve Hours
Use this command to approve a selected range of hours transactions.

If the Approval Required field in the People Parameters (bpmdm0100m000) session is cleared, this command is available.

Undo Approve Hours
Use this command to undo the approval of a selected range of hours transactions.

If the Approval Required field in the People Parameters (bpmdm0100m000) session is cleared, this command is unavailable.

Global (Undo) Approve Hours and Expenses
Starts the Global (Undo) Approve Hours and Expenses (bptmm1202m000) session.
Process Hours and Expenses
Starts the Process Hours and Expenses (bptmm1203m000) session.
Intercompany Trade Orders
Starts the Intercompany Trade Orders (tcitr3100m000) displaying the intercompany trade orders for the selected employee, year and period.
Intercompany Trade Orders - Sales Lines
Starts the Intercompany Trade Orders - Sales (tcitr3100m200) session displaying the intercompany trade orders for the selected line.
General Hours
Starts the General Hours (bptmm1111m200) session.
Project Hours
Starts the Project Hours (bptmm1111m000) session.
Project (PCS) Hours
Starts the Project (PCS) Hours (bptmm1170m000) session.
Production Order Hours
Starts the Production Order Hours (bptmm1120m000) session.
Assembly Hours
Starts the Assembly Hours (bptmm1160m000) session.
Service Order Hours
Starts the Service Order Hours (bptmm1130m000) session.
Work Order Hours
Starts the Work Order Hours (bptmm1140m000) session.
Project Expenses
Starts the Project Expenses (bptmm1111m100) session.
Hours and Expenses History
Starts the Hours and Expenses History (bptmm2800m000) session.
Employees by Team
Starts the Employees by Team (tcppl0150m000) session.
Print Hours and Expenses
Starts the Print Hours and Expenses (bptmm1400m000) session.