Generate Maintenance Plan (tsspc2200m000)

Use this session to generate maintenance plans for a range of Installation groups.

Note
  • The start date for the serialized items is equal to the effective date of the Serialized Items (tscfg2100m000) session. The effective date is the installation time of the serialized item and if it is not filled then it is the delivery time and if the delivery time is also not filled then it is creation time of the serialized item.
  • The serialized item's start value is equal to the planned dependent value that you defined for the serialized item in the Planned Activities (tsspc2100m000) session.

 

Installation Group

The From and To fields define a range of: installation group.

Installation Group

The From and To fields define a range of: installation group.

Time

The From and To fields define a range of: time period considered to generate the plan.

Time

The From and To fields define a range of: time period considered to generate the plan.

Only Generate Maintenance Plan for Active Contract Period

If this check box is selected, LN considers only the active contract period for generation of the plan.

Consider Last Planned Activity Date by Scenario Line

If this check box is selected, LN considers the last planned activity date for generation of the plan.

Consider Planned Until Time of Serialized Item

If this check box is selected, LN considers the serialized item's planned until time.

Consider Maintenance Cycle

If this check box is selected, LN considers the maintenance cycle for generation of the plan.

Consider Life Cycle

If this check box is selected, LN considers the item's life cycle for generation of the plan.

Start Maintenance Cycle

The options to initiate the maintenance cycle.

Consider Last Planned Activity Date as Maintenance Cycle Start Time

If this check box is selected, LN considers the last planned activity date as maintenance cycle start time.

Use service department of reference activity for planned activities

If this check box is selected, LN uses the service department of the reference activity for planned activities.

Block Maintenance Planning if Required Resources Cannot be created

If this check box is selected, LN blocks the generation of the maintenance plan if the required resources cannot be created.

Delete Planned Activities for Scenario Line

If this check box is selected, LN deletes the planned activities for the selected maintenance scenario line.

Delete All Planned Activities in Range

If this check box is selected, LN deletes all the planned activities in the specified range.

Activity Status

The status of the activities being generated for the maintenance plan.

Simulation

If this check box is selected, LN simulates the plan.

Process Report
Error Report
Information Report

If this check box is selected, LN prints the plan information report.