Group Sets for Work Orders (tsspc2190m100)

Use this session to view and maintain group sets generated from group planning activity sets for work orders.

 

Start Date Groups

The start date of the group set. LN displays the group sets with a start date later than the specified date.

Finish Date Groups

The finish date of the group set. LN displays the group set with a finish date earlier than the specified date.

Group Set

The unique ID of the group set.

Activity Origin

The origin of the activities in the group sets for work order. By default, the value is set to Work Order.

Allowed values

Activity Origin

Target Number of Groups

The number of groups you create for the group set.

Note

The value in this field is defaulted from the Attribute Group - Preferred Resources (tsspc0120m100) session.

Existing Number of Groups

The number of groups available for the group set.

Sort Method

The method to sort the work order activities in a group set.

Note

This value is defaulted from the Service Planning Parameters (tsspc0100m000) session.

Allowed values

Sort Method

Plan Method

The method to plan the work order activities in a group set.

Note

This field is enabled only if the Activity Origin is set to Service Order or Planned Activity.

Allowed values

Plan Method

Respect Earliest Start Time

If this check box is selected, LN considers the earliest start time to plan the work order activity.

Note

The value in this field is defaulted from the Respect Earliest Start Time field defined in the Service Planning Parameters (tsspc0100m000) session.

Respect Material Availability Date

If this check box is selected, LN considers the Material Availability Date specified for the work orders in the Service Planning Parameters (tsspc0100m000) session, to schedule the work order activities in a Group Set.

Note
  • This field is visible only if the Check Material Availability check box in the Service Order Parameters (tssoc0100m000) session or the Check Material Availability check box in the Work Order Parameters (tswcs0100m000) session is selected.
Planned Start Time

The planned start date and time of the first activity in the specified group set.

Note

The value in this field is defaulted from the groups (defined in Groups for Work Orders (tsspc3100m100) session) linked to the group set.

Planned Finish Time

The planned finish date and time of the last activity in the specified group set.

Note

The value in this field is defaulted from the groups (defined in Groups for Work Orders (tsspc3100m100) session) linked to the group set.

Total Activity Duration

The cumulative duration of travel for all the activities in the group set.

Note

The value in this field is defaulted from the groups (defined in Groups for Work Orders (tsspc3100m100) session) linked to the group set.