| To estimate service order costsYou can specify a service order's requirements in the
following sessions: - Service Order Estimated Material Costs (tssoc2120m000)
- Service Order Estimated Labor Costs (tssoc2130m000)
- Service Order Estimated Other Costs (tssoc2140m000)
A cost component, used as a
method for cost control must be related to every estimated cost line and actual
cost line. Purpose to estimate service order costs - To budget the costs
(that are task setting) of carrying out the service order when price agreements
are fixed.
- To ensure that the
materials are available by allocating or ordering the required materials.
- To ensure that the
service engineers are available by allocating the required service engineers.
- To ensure that the tools
are available by allocating the required tools.
Note - If you add a reference activity to a service order, the reference
activity's cost lines are copied to the service order's requirements.
- If you generate a
service order from a planned activities, a call, or a field change order, the
cost lines linked to the constituent reference activities are copied to the
service order's requirements.
| |