Print Principal's Project-Control Report (tpppc4412m000)

Use this session to print control reports for the principal. Reports can be based on the selection of project, financial result status, element, and sort argument.

 

Period to

The year up to which the level is to be printed.

/

The period to which the level is to be printed.

Currency

The currency.

Related topics

Commitments

If this check box is selected, the commitments are taken as costs.

Sort By

Indicates how you want to sort the level.